Upgrade Website For ABC Software Private Limited

Project Scope for Website Upgrading Project

I would like to inform you that, currently our company ABC Software Private Limited is facing certain challenges in their functional and operational activities. In order to grab new consumers and retain existing consumers we would like to upgrade our website. As we deliver online service to our consumers therefore, the website plays a crucial role. The commercial success and commercial consequences of our company is somewhere dependent on its online presence and response. We have highlighted certain resources and essential elements those are needed to upgrade the current website. In order to redesign and redevelop a responsive and user friendly website for our company we need capital, commercial support from your end.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

We are expecting that, if we get commercial and economic support from your end then we would be able to reconstruct our website and we will definitely obtain positive ROI in the coming 5 years. We would also gain commercial support and competitive advantages also. I wish you will definitely support us but still we are waiting for your valuable response.

The scope of the project is to design and develop or reconstruct the existing website of ABC software Private Limited. For accomplishing the “website upgrading project“, supporting resources and stakeholders should be assigned. At the project initiation phase, this large project must be subdivided into segments and individuals are required to be assigned to each of the segment. The lessons learned from the study of project management practices and its application in knowledge areas are applied while reconstructing the existing website project. Professional commitments from project team members are also crucial and the project charter considers the team operation principles also. The other instance of project scope is stakeholders name their responsibilities and the possible risk along with development of a risk register.

The project has a commercial negative consequence to both their clients and employees.  In the new era of technology it is much important for any business organization to develop an attractive, user friendly and easy to response website which can be easily handled by both their consumers and working employees. These features will help the company to grab new consumers and at the same time retain existing consumers also.  ABC software Private Limited offers accounting software system to the consumers. The company serves both online and offline services to their consumers therefore, non responsive website was negatively impacting its success line, In order to resolve operational and functional challenges and gathered consumer’s feedback the company decided to improve the existing structure of the website.

Operational and Functional Challenges Faced by ABC Software Private Limited

In order to redesign and reconstruct the current website the assigned project designer requires gathering both functional and non functional requirements. Proper usability of the information will help ABC Private Limited to improve their website to another level. The current website looks extremely back-dated, it has very bad user experiences and it is also hard to navigate. Other similar types of organizations offer much better services and products to their clients. Thus, the competitive challenges are also increasing day by day. The redesign and reconstruction of the website become very crucial to gain commercial revenue and competitive advantages as well.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Before redesigning and reconstructing the website the company needs to build additional features and functionalities as well without redo the entire website. The marketing manager of ABC software Private Limited needs to consider the advanced marketing strategies while reconstructing the website. The content of the websites should also be updated. Besides this, the assigned project manager must ensure that the website is completely optimized by the Senior Executive Officers of the company. The marketing efforts will be helped also if theses feature are added to the website. Apart from this, security is the other concern on which the design must keep their focus. If security of the system lags then it will hamper regular expected commercial success of ABC software Private Limited.

Enough amounts of resources should also be identified to gather information to design the new business for the software product delivery company. Not only the features but paralelly leadership, motivation and supporting environment are also required to reconstruct the official website. After accomplishing redesign of the website it must be promoted by the marketing department of the company. In order to meet the project objectives the company should analyze their goals and success criteria at the project initiation phase. Moreover, it can be said that the designed and system developer requires incorporating advanced functional abilities to obtain positive Return on Investment (ROI). The project manager and the project team members ought to link the project back to the company’s over arching business marketing strategies. It is assumed that if the company feasibly complete the development of a strong business case then the internal buy in of the company will also improved.

WBS

Task Name

Duration

Start

Finish

Resource Names

Cost

0

Website upgradation project for ABC Software Private Limited

82 days

Wed 1/31/18

Thu 5/24/18

$123,112.00

1

   Project initiation

17 days

Wed 1/31/18

Thu 2/22/18

$54,720.00

1.1

      Developing project scope statement

5 days

Wed 1/31/18

Tue 2/6/18

Designer and developer

$1,120.00

1.2

      Setting target audience

6 days

Wed 2/7/18

Wed 2/14/18

HR manager

$960.00

1.3

      Analyzing current content of the website

5 days

Wed 2/7/18

Tue 2/13/18

Project manager

$1,200.00

1.4

      Resource identification and information gathering

6 days

Thu 2/15/18

Thu 2/22/18

Project manager, Sponsor[1]

$51,440.00

1.5

      Milestone 1: Completion of project initiation phase

0 days

Thu 2/22/18

Thu 2/22/18

$0.00

2

   Project planning

11 days

Fri 2/23/18

Fri 3/9/18

$3,688.00

2.1

      Stakeholder management plan

6 days

Fri 2/23/18

Fri 3/2/18

Project manager

$1,440.00

2.2

      Risk management plan

8 days

Fri 2/23/18

Tue 3/6/18

finance manager

$1,408.00

2.3

      Functional and non functional requirement gathering to update the websites

3 days

Wed 3/7/18

Fri 3/9/18

IS manager

$840.00

2.4

      Milestone 3: Completion of project planning phase

0 days

Fri 3/9/18

Fri 3/9/18

Project manager

$0.00

3

   Project redesign and redevelopment

32 days

Mon 3/12/18

Tue 4/24/18

$10,160.00

3.1

      UML diagram structuring

6 days

Mon 3/12/18

Mon 3/19/18

Designer and developer

$1,344.00

3.2

      Designing data model

5 days

Tue 3/20/18

Mon 3/26/18

Application programmer

$960.00

3.3

      Font end modification

8 days

Tue 3/20/18

Thu 3/29/18

IS manager

$2,240.00

3.4

      Back end modification

7 days

Tue 3/27/18

Wed 4/4/18

Designer and developer

$1,568.00

3.5

      Database modification

5 days

Thu 4/5/18

Wed 4/11/18

Designer and developer

$1,120.00

3.6

      Simulation

9 days

Thu 4/5/18

Tue 4/17/18

Application programmer

$1,728.00

3.7

      Final approval from the project manager

5 days

Wed 4/18/18

Tue 4/24/18

Project manager

$1,200.00

3.8

      Milestone 4: Completion of project design and development phase

0 days

Tue 4/24/18

Tue 4/24/18

$0.00

4

   Project testing

10 days

Wed 4/25/18

Tue 5/8/18

$2,000.00

4.1

      Unit testing

5 days

Wed 4/25/18

Tue 5/1/18

tester

$1,000.00

4.2

      integrated testing

2 days

Wed 5/2/18

Thu 5/3/18

tester

$400.00

4.3

      Acceptance testing

3 days

Fri 5/4/18

Tue 5/8/18

tester

$600.00

4.4

      Milestone 4: Completion of project testing phase

0 days

Tue 5/8/18

Tue 5/8/18

$0.00

5

   Project closure

12 days

Wed 5/9/18

Thu 5/24/18

$52,544.00

5.1

      Post website maintenance planning

5 days

Wed 5/9/18

Tue 5/15/18

Project manager

$1,200.00

5.2

      Stakeholder signoff

6 days

Wed 5/16/18

Wed 5/23/18

Designer and developer

$1,344.00

5.3

      Submission of final draft

1 day

Thu 5/24/18

Thu 5/24/18

Sponsor[1]

$50,000.00

5.4

      Milestone 5: Completion of project closure phase

0 days

Thu 5/24/18

Thu 5/24/18

Project manager

$0.00

Risk Id

Name of the risk

Impact

Probability

Ranking

Mitigation strategies

R12

Lack of communication

Major 4

Possible 3

High 12

To implement open communication

R2

Lack of technical skills among team members

Major 4

Probable 4

Extreme 16

To arrange on job training and development class for the working development team members

R6

Improper time and cost management

Catastrophic 5

Rare 1

Medium

Feasibility study and proper estimation of budget is requited at the project progress period

R20

Operational failure

Insignificant 1

Unlikely 2

Low 2

Experienced operation experts are needed to be hired by the project manager and project team members

Name of the stakeholders

Power

Interest

Project manager

High

The project manager is interested to accomplish the project within the assigned time and estimated budget

finance manager

High

The interest of the assigned finance manager is to estimate the project budget by making a feasibility study before initiating the project

IS manager

Low

The responsibility of the IS manager is to consider all website upgrade specifications to ensure that functionalities and features are available to the upgraded website

Designer and developer

High

The designer and developers are interested to design and develop the system in such a way so that all their employees and consumers feel free to use it whenever needed

Tester

Low

The interest of the project tester is to test the system before launching it in the competitive marketplace

Application programmer

High

The application programmer is interested to use their programming ability to model the data as per the objectives, aim and project goals.

HR manager

Low

The HR manager’s interest is to assign an accurate project team using performance measurement matrix. It is defined that, if theses specifications are followed properly then the assigned project team will contribute 100 percent of their interest.  

Sponsor

High

The interests of the project sponsors are to invest needful amount of capital to the ABC software Private Limited so that they can utilize the resources wisely whenever needed.

In order to develop any project it is crucial for the project team members and project manager to follow certain operating principles. It is assumed that if these team operation principles and specifications are all followed properly, then the chances of intra team conflict will be completely resolved. The rules for team engagement or the team operating principles can go longer way for minimizing the rate of internal tea conflict. It will also help to build trust among the project team members. The lists of team operating principles are as follows which needs to be followed by the project team members and project manager as well.

  • The team must owe the company terms and policy designed by the management team
  • Instead of making assumptions the team should focus on business needs
  • The team must focus on major issues instead of small issues
  • The company must follow regular meeting and share all information
  • The company should make clear decisions based on project requirements

Requirements Gathering for Website Redesign and Reconstruction

 In order to conduct the project towards success line, it is much important for the assigned project manager and project team members to consider each and every project management practice. Collaborative, integrated design and structure of the project will provide commercial success and competitive advantages to the project team members. While allocating the project team the team operating principle are also needed to be considered by the project manager and team members. It is assumed that stakeholder register, risk register and milestone scheduling of the project are much crucial to accomplish the project within estimated time and budget.

From the project management prcatices it is also learned that, there are certain knowledge areas that must be analyzed to deliver a successful project. It is also learned that, before listing target audience possible risks need to be identified, analyzed and prioritized accordingly. Based on the complexity of these risks the risk register should be developed. The other knowledge areas which fall under the project manager’s concern include professional communication strategies, HR strategies and quality management plan.

The project team members ought to be committed to their assigned job roles and responsibilities and these will be followed to successfully govern website upgradation project. In other ways employee commitment is the ultimate key for project success.

References

Buenviaje, M. G., Morcilla, G. P., FernanRefozar, R., Macalalad, J. A., and Laguador, J. M. 2016. Role of Effective Communication in the Organizational Commitment and Employee Behavior as Input to Human Resource Management. Quarterly Journal of Business Studies, 2(4), 193-200.

Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., and  Wang, Q. 2015. Implementing educational innovations at scale: Transforming researchers into continuous improvement scientists. Educational Policy, 29(1), 257-277.

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., and de Almeida, L. F. M. 2014. Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.

Joslin, R., and Müller, R. 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.

Kaiser, M.G., El Arbi, F. and Ahlemann, F., 2015. Successful project portfolio management beyond project selection techniques: Understanding the role of structural alignment. International Journal of Project Management, 33(1), pp.126-139.

Leveson, N., 2015. A systems approach to risk management through leading safety indicators. Reliability Engineering and System Safety, 136, pp.17-34.

Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., and Villanueva, P. 2014. Project risk management methodology for small firms. International Journal of Project Management, 32(2), 327-340.

Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project risk management methodology for small firms. International journal of project management, 32(2), pp.327-340.

Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley and Sons.

Matyas, D. and Pelling, M., 2015. Positioning resilience for 2015: the role of resistance, incremental adjustment and transformation in disaster risk management policy. Disasters, 39(s1), pp.s1-s18.

McNeil, A.J., Frey, R. and Embrechts, P., 2015. Quantitative Risk Management: Concepts, Techniques and Tools-revised edition. Princeton university press.

Mir, F. A., and Pinnington, A. H. 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Sanchez, M. A. 2015. Integrating sustainability issues into project management. Journal of Cleaner Production, 96, 319-330.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.