Project Management: Cloud Based SAP Instance Implementation For Dai-Ichi Corporation

Objectives and high-level requirements

  The objectives of the project are as follows:

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
  • To deploy the same platform into the Oceania operations
  • To deploy the SAP instance on the cloud
  • To facilitate SAP instance to be managed out of Europe

The high-level requirements for the project include:

  • 2X Database servers
  • 2X Application servers
  • 3X Web Services Layer servers
  • X86 Image- per instance
  • SAP Cloud instance
  • JIRA

The project can be controlled by utilizing methods that are as follows:

Conducting regular meetings: It is very much necessary to conduct regular meetings in so that the project team members can able to discuss about the project hurdles as well as can update the tasks of the project effectively. Team meetings involves identification of dependencies as well as risks that are assigned to the tasks.

Using earned value analysis: Earned value analysis is one of the project control technique that mainly helps in measuring the performance of the project. It is one of the technique, which not only assists in quantifying project progress but also helps in controlling project. It is very much necessary to keep an eye on the CPI as well as SPI, which are related with earned value analysis in order to ensure that the entire project will be completed within the estimated budget and time.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Using critical path analysis: If the activities that are related with critical path is delayed then the project completion date gets impacted and therefore inn order to monitor as well as control the project it is necessary to keep proper track on the critical path of the project.

The resources that are required in the project are listed in the table below:

Resource Name

Type

Initials

Max. Units

Std. Rate

Accrue At

Base Calendar

Project manager

Work

P

100%

$2,000.00/day

Prorated

Standard

Paulo-SAP Expert

Work

P

100%

$2,000.00/day

Prorated

Standard

Sanjay-Cloud architect

Work

S

100%

$7,500.00/month

Prorated

Standard

June-SAP expert

Work

J

100%

$7,500.00/ month

Prorated

Standard

Larry jones-LAMP stack specialist

Work

L

100%

$3,500.00/ month

Prorated

Standard

Jenny Harvey-Linux Administrator+ LAMP

Work

J

100%

$3,250.00/ month

Prorated

Standard

Amazon cloud infrastructure( X 86 image-Per instance)

Work

100%

$2,750.00/ month

Prorated

Standard

SAP Cloud instance-Site License for Australia

Material

$200,000.00

Prorated

JIRA

Material

J

$50.00

Prorated

Travel and accommodation expenses for Paolo

Work

100%

$10,000.00/month

Prorated

Standard

It is estimated that the cloud based SAP instance for Dai-Ichi Corporation will be completed successfully within the budget that is around $864,668.75. The table below helps in reflecting the cost that is needed to complete each of the activities of the project.

Task Name

Duration

Cost

Creating cloud based SAP instance for Dai-Ichi Corporation Australia

60 days

$864,668.75

   Initiation Phase

4 days

$9,387.50

       Defining scope of the project

0.5 days

$1,000.00

      Defining project time

1 day

$2,375.00

      Defining cost constraints of the project

1 day

$550.00

      Defining high level requirements

0.5 days

$1,462.50

       Forming project team

1 day

$4,000.00

       Milestone 1: Completion of project initiation phase

0 days

$0.00

   Planning phase

6 days

$211,650.00

      Developing project plan

1 day

$2,550.00

      Creating schedule of the project

1 day

$375.00

      Creating detailed budget for the project

2 days

$4,750.00

      Obtaining sign off on plan

0.5 days

$1,437.50

      Getting approval for the project

0.5 days

$2,000.00

       Signals approval by steering committee

1 day

$200,537.50

       Milestone 2: Completion of planning phase

0 days

$0.00

   Design/build phase

36 days

$220,818.75

      Detailed requirement gathering

1 day

$202,375.00

      Security requirements

1 day

$162.50

      Infrastructure planning

1.5 days

$206.25

      System operation strategy

1.5 days

$825.00

      Training preparation

2 days

$4,000.00

      Configuration and development

2 days

$5,100.00

      Unit/Process business acceptance testing

3 days

$525.00

      Infrastructure implementation

5 days

$500.00

      Implement AWS Cloud Infrastructure

5 days

$0.00

      Develop SAP on the System

4 days

$0.00

      Test the SAP on the AWS Cloud Infrastructure

3 days

$0.00

      Find Bugs and Glitches

2 days

$0.00

      Troubleshoot Issues

2 days

$0.00

      Make Some Modifications in System Function

3 days

$7,125.00

      Milestone 3: Completion of design/Build phase

0 days

$0.00

   Go live phase

10 days

$414,437.50

      End user training

3 days

$7,500.00

      Business simulation

2 days

$0.00

      End user practice in the system

1 day

$200,375.00

      Infrastructure finalization

1 day

$200,137.50

       Data migration to production

2 days

$4,050.00

      Pre-go live operations

1 day

$2,375.00

      Milestone 4: Completion of go live phase

0 days

$0.00

   Closure phase

4 days

$8,375.00

      Post-project review

1 day

$2,000.00

      Stakeholder sign off

1 day

$2,375.00

      Documentation

2 days

$4,000.00

      Milestone 5: Completion of project closure phase

0 days

$0.00

Task Name

Duration

Start

Finish

Creating cloud based SAP instance for Dai-Ichi Corporation Australia

60 days

Mon 4/9/18

Fri 6/29/18

   Initiation Phase

4 days

Mon 4/9/18

Thu 4/12/18

       Defining scope of the project

0.5 days

Mon 4/9/18

Mon 4/9/18

      Defining project time

1 day

Mon 4/9/18

Tue 4/10/18

      Defining cost constraints of the project

1 day

Tue 4/10/18

Wed 4/11/18

      Defining high level requirements

0.5 days

Wed 4/11/18

Wed 4/11/18

       Forming project team

1 day

Thu 4/12/18

Thu 4/12/18

       Milestone 1: Completion of project initiation phase

0 days

Thu 4/12/18

Thu 4/12/18

   Planning phase

6 days

Fri 4/13/18

Fri 4/20/18

      Developing project plan

1 day

Fri 4/13/18

Fri 4/13/18

      Creating schedule of the project

1 day

Mon 4/16/18

Mon 4/16/18

      Creating detailed budget for the project

2 days

Tue 4/17/18

Wed 4/18/18

      Obtaining sign off on plan

0.5 days

Thu 4/19/18

Thu 4/19/18

      Getting approval for the project

0.5 days

Thu 4/19/18

Thu 4/19/18

       Signals approval by steering committee

1 day

Fri 4/20/18

Fri 4/20/18

       Milestone 2: Completion of planning phase

0 days

Fri 4/20/18

Fri 4/20/18

   Design/build phase

36 days

Mon 4/23/18

Mon 6/11/18

      Detailed requirement gathering

1 day

Mon 4/23/18

Mon 4/23/18

      Security requirements

1 day

Tue 4/24/18

Tue 4/24/18

      Infrastructure planning

1.5 days

Wed 4/25/18

Thu 4/26/18

      System operation strategy

1.5 days

Thu 4/26/18

Fri 4/27/18

      Training preparation

2 days

Mon 4/30/18

Tue 5/1/18

      Configuration and development

2 days

Wed 5/2/18

Thu 5/3/18

      Unit/Process business acceptance testing

3 days

Fri 5/4/18

Tue 5/8/18

      Infrastructure implementation

5 days

Wed 5/9/18

Tue 5/15/18

      Implement AWS Cloud Infrastructure

5 days

Wed 5/16/18

Tue 5/22/18

      Develop SAP on the System

4 days

Wed 5/23/18

Mon 5/28/18

      Test the SAP on the AWS Cloud Infrastructure

3 days

Tue 5/29/18

Thu 5/31/18

      Find Bugs and Glitches

2 days

Fri 6/1/18

Mon 6/4/18

      Troubleshoot Issues

2 days

Tue 6/5/18

Wed 6/6/18

      Make Some Modifications in System Function

3 days

Thu 6/7/18

Mon 6/11/18

      Milestone 3: Completion of design/Build phase

0 days

Mon 6/11/18

Mon 6/11/18

   Go live phase

10 days

Tue 6/12/18

Mon 6/25/18

      End user training

3 days

Tue 6/12/18

Thu 6/14/18

      Business simulation

2 days

Fri 6/15/18

Mon 6/18/18

      End user practice in the system

1 day

Tue 6/19/18

Tue 6/19/18

      Infrastructure finalization

1 day

Wed 6/20/18

Wed 6/20/18

       Data migration to production

2 days

Thu 6/21/18

Fri 6/22/18

      Pre-go live operations

1 day

Mon 6/25/18

Mon 6/25/18

      Milestone 4: Completion of go live phase

0 days

Mon 6/25/18

Mon 6/25/18

   Closure phase

4 days

Tue 6/26/18

Fri 6/29/18

      Post-project review

1 day

Tue 6/26/18

Tue 6/26/18

      Stakeholder sign off

1 day

Wed 6/27/18

Wed 6/27/18

      Documentation

2 days

Thu 6/28/18

Fri 6/29/18

      Milestone 5: Completion of project closure phase

0 days

Fri 6/29/18

Fri 6/29/18

The figure that is provided below is the Gantt chart, which is one of the graphical tool that helps in reflecting activities as well as tasks that are needed to be performed against time. In this project, the Gantt chart reflects the activities that are needed to be completed in order to execute the project of SAP within organization “Dai-Ichi Corporation” in 12 weeks.

The figure that is provided above helps in highlighting the critical path of the project which is considered as the longest sequence of activities that are needed to be completed on time to complete the entire project on due date.  The project activities that are present on the critical path cannot be initiated until its predecessor is complete. For example, Requirement gathering for the project cannot be started until project is approved by the steering committee.

Communication Type

Objective

Medium

Frequency

Audience

Owner

Project kick off meeting

 Project kick off meeting is mainly arranged in order to introduce the project objectives and for discussing about goals and objectives of the project.

Face to face

Once

Project sponsor

Project team

Project manager

Project team meeting

 Project team meeting is arranged in order to know about the difficulties that are faced by the project stakeholders.

Face to face

Conference

 As required

Project team

Project manager

Monthly status meeting

 Monthly status meeting is mainly arranged in order to track the status of the project.

Face to face

Presentation

Conference

Monthly

Team leaders

Project manager

Risk

Description

Probability

Consequence

Mitigation

Schedule slippage

 Due to slippage of project schedule, the project manager faces difficulty in completing the entire project on time and budget.

 High

High

 It is very much necessary to track the budget and schedule of the project with the help of earned value analysis.

Budget shortfall

 If the resources of the project are misused then the project manager can face budget shortfall.

High

High

It is very much necessary to utilize the resources of the project effectively in order to reduce issues and challenges related with project budget.

Security issues

 If proper security measures are not utilized then important data and information related with business can be  leaked or can be misused.

Medium

High

It is necessary to have proper authentication in order to reduce security related issues and challenges

Chih, Y.Y. and Zwikael, O., 2015. Project benefit management: A conceptual framework of target benefit formulation. International Journal of Project Management, 33(2), pp.352-362.

Conforto, E.C., Salum, F., Amaral, D.C., da Silva, S.L. and de Almeida, L.F.M., 2014. Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), pp.21-34.

De Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its effects on project success: Cross-country and cross-industry comparisons. International Journal of Project Management, 33(7), pp.1509-1522.

Hornstein, H.A., 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298.

Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392.

Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project risk management methodology for small firms. International journal of project management, 32(2), pp.327-340.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Riol, H. and Thuillier, D., 2015. Project management for academic research projects: balancing structure and flexibility. International Journal of Project Organisation and Management, 7(3), pp.251-269.

Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.

Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), pp.1382-1394.

The network diagram that is provided above helps in reflecting the activities that are interrelated with each other from project initiation to closure phase. The interrelation that are provided above with project activities helps in calculating the total time for the project. In addition to this, it is identified that with the help of the interdependencies that is highlighted within the network diagram one can complete the project as per the sequence.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.