Procurement Management Plan For Able Communications

Procurement Management Approach

The plan is focused on defining the procurement requirements for the project and process for developing the documentation for procurement through contract closure. This plan illustrates the approach that will be followed to manage the procurement requirements for the project. Further, the definition of procurement is also provided to describe the items that will be procured and under what conditions. The contract type that is being utilized for this particular project and process through which contracts must be approved is also mentioned in this plan. The decision criteria for awarding contracts along with suitable methods for vendor management are also highlighted in this plan. This plan also illustrates the metrics that will be used for the procurements activities related to the project.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The procurement for this particular project to acquire staffing solutions for the Able Communications will be carried out in different phases as illustrated below:

Selection of the contract approach – A work description that have to be outsourced will be developed by the project team. The procurement team will find the answers to specific questions that are required for determining the approach to obtain the required goods or services (Pheng 2018).

Solicitation of bids – It is the process to request price or required information from the bidders. The bids are solicited in either form of Request for Quote (RFQ) or Request for Proposal (RFP). For this particular project, RFQ (Request for Quote) has been selected as the suitable method to acquire staffing solutions for Able Communications. The price required for the services will be quoted by the bidder and the contract will be awarded to that bidder who quotes lowest price along with capability to meet the quality as well as schedule requirements of the project

Evaluation of Bids – The bids from different bidders will be evaluated and then the lowest bid that is having the lowest total price will be considered suitable for the contract (Turner 2017).

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Awarding the contract – After selection of a bidder, a team member of the project team will validate the bid conditions as well as the contract with potential contractor. The detailed discussion of the project requirements will be conveyed to the bidder so that the project could be accomplished according to quality and schedule requirements.

Managing the contracts – After awarding the contract to potential bidder, the project team will keep track of the contractor performance in comparison to performance criteria as mentioned in the contract (Jo, Lee and Pyo 2018).

Logistics and expediting – Finally, the materials or equipment that has been procured for the project will be transported and inventoried for closure of the contract.

The items that have to be procured for this project on acquiring staffing solutions for Able Communications are listed as below:

 Development of management programs – This item will comprise of developing a program for training purposes as well as recruitment of staffs. This item have to be made available so that the skills and knowledge of the staffs could be evaluated and proper training could be provided (Allen et al. 2015). The development of management programs is necessary for this project to ensure that the organizational goals and objectives could be fulfilled by the staffing solution. It will be procured internally as management of the organization will be responsible for developing the management programs.

Procurement Definition

External professional services – This item will be procured through outsourcing as speakers or advisors will be hired to conduct seminars on personal development and career growth. It is important for the project so that the recruited staffs could excel in their work and meet desired expectations of the organization.

Software as well as hardware – Some hardware as well as software will be required for training purposes so that staffs being outsourced will be able to handle their work in an efficient manner (De Araujo et al. 2017). The software and hardware will be procured from external third party vendors hence this item will be procured externally.

Marketing spend – This item will comprise of the marketing requirements so that the bidders could be encouraged to place their bids for the contract on providing staffing solutions to Able Communications. This item will be procured both internally as well as externally as the marketing strategies will be developed internally within the organization and externally as Advertisement or other agencies will contacted to spread the awareness of contract for staffing solutions (Lloyd-Walker and Walker 2015).

For this particular project on staffing solution for Able Communications, it has been identified that required items will be procured with the help of two major types of contract. The types of contract that will be used for the items to be procured are Firm Fixed Price (FFP) contract and Cost plus Fixed Fee (CPFF) contracts.

The Firm Fixed Price (FFP) contract will be used for the items that will procured internally by the organization. This type of contract will incur a lump sum cost to the organization and it is suitable when the scope is clear (Decarolis 2014). This contract type will be used for two items that is Development of management programs and Marketing spend that includes development of marketing strategy for the contract.

Cost plus Fixed Fee (CPFF) contract will be used for the items that have to be procured externally as the organization will have to pay for the products or services acquired from the seller (Chen et al. 2015). This type of contract will be used for procuring external professional services, software and hardware along with marketing for the contract.

The approval of the contract to procure staffing solution for Able Communications will be carried out through steps as below:

  • The project team will review the contract and forward it to Vice President of the organization.
  • The contractor will be reviewed by the Vice president and Risk manager and signed off.
  • Then it will be mailed to the CEO of the organization for review and approval.
  • The CEO will review and sign-off the contract then it will be emailed to vendor for signature.

The major criteria being used by the contract review board for making decisions to award a contract are as below:

  • Reputation of the contractor – The record of the contractor will be analyzed and reputation of the determined contractor in the market will be researched.
  • Value of contracts being completed by the contractor – The total number of projects being completed by the contractor will be analyzed along with the total value of the completed projects.
  • Commitment towards quality and schedule requirements – The commitment of the contractor with respect to quality and maintaining the schedule requirements will be evaluated.

The decision for awarding the contract to a particular contractor will be finalized only after successful assessment of the contractor in terms of the above identified criteria.

The project team as well as the purchasing and contracts department will take certain roles and responsibilities for ensuring that appropriate levels of quality is maintained. Some of the roles and responsibilities are listed as below:

  • The project team will develop a quality management plan that will be followed by the purchasing and contracts department to maintain the quality requirements.
  • The project team will also include a quality analyst so that quality outcomes are achieved during procurement of products or services.
  • The purchasing and contracts department will include a supervisor so that quality of materials during procurement could be assessed properly.

The performance metrics that will be utilized for the procurement activities are described as below:

Cost per product: This metrics will used to determine whether the cost being taken by the contractor for each product as per the market.  

Quality of delivered product: The products that are delivered will be assessed in terms of quality to ensure the procurement activity is successful.

On time delivery: This metric relates to delivery of the required materials on time so that the procurement activity is completed successfully.

References:

Allen, M., Herring, K., Moody, J. and Williams, C., 2015. Project procurement: Impact of contract incentives and penalties. International Journal of Global Business, 8(2), p.1.

Chen, Q., Xia, B., Jin, Z., Wu, P. and Hu, Y., 2015. Choosing appropriate contract methods for design-build projects. Journal of Management in Engineering, 32(1), p.04015029.

De Araújo, M.C.B., Alencar, L.H. and de Miranda Mota, C.M., 2017. Project procurement management: A structured literature review. International Journal of Project Management, 35(3), pp.353-377.

Decarolis, F., 2014. Awarding price, contract performance, and bids screening: Evidence from procurement auctions. American Economic Journal: Applied Economics, 6(1), pp.108-32.

Jo, S.H., Lee, E.B. and Pyo, K.Y., 2018. Integrating a Procurement Management Process into Critical Chain Project Management (CCPM): A case-study on oil and gas projects, the piping process. Sustainability, 10(6), p.1817.

Lloyd-Walker, B. and Walker, D., 2015, April. Collaborative project procurement arrangements. Project Management Institute.

Pheng, L.S., 2018. Project Procurement Management. In Project Management for the Built Environment (pp. 177-193). Springer, Singapore.

Turner, J.R., 2017. Contracting for project management. Routledge.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.