Planning Documents For New Hybrid Handheld Game Console Project

Part A – Planning documents for new hybrid handheld game console project

The report discusses the activity-on-node, Gantt chart and critical path for the project plan of new hybrid handheld game console project. The main activities of the project plan are requirements specification, content specification, design, implementation, integration and subcontracting. In this report, the project management tool such as Gantt chart is used to represent the time for each project activities needed to complete the project work. Martinelli and Milosevic (2016) have stated that it is simple and easier to understand the project progress. The report also discusses the Precedence network diagrams which is visual representation technique which can depict the project activities involved into the project.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Problem 1: Activity-on-node network

The activity-on-node is the term of project management which is referred to precedence diagramming method that uses boxes to present the schedule activities of entire project plan. The boxes and nodes are being associated from staring to finish with arrows to present the reasonable representation of the dependencies among the schedule activities (Too and Weaver 2014). In terms of project management, float or total slack is sum of time that the project job is delayed without causing delay to project completion time.

Figure 1: Activity on node

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

(Source: Created by author)

The project schedule is shown in the table below with starting time, finishing time, floats and other information based on the activities in the network diagram.

WBS

Task Name

Duration

Start

Finish

Resource Names

WBS Predecessors

Total Slack

0

New hybrid handheld game console project_Problem 1

54 wks

Mon 12/24/18

Fri 1/3/20

0 wks

1

Requirements specification

13 wks

Mon 12/24/18

Fri 3/22/19

0 wks

1

 Entire product

3 wks

Mon 12/24/18

Fri 1/11/19

Developer, Market Researcher, Project Lead, Project Manager, Software Engineer, System Analyst

0 wks

2

 Software

5 wks

Mon 1/14/19

Fri 2/15/19

Developer, Project Manager, Software Engineer, System Analyst

1

0 wks

3

 Hardware

4 wks

Mon 2/18/19

Fri 3/15/19

Developer, Project Manager, Software Engineer, System Analyst

1,2

0 wks

4

 Market research

1 wk

Mon 3/18/19

Fri 3/22/19

Market Researcher, Project Lead, Project Manager

2,3

0 wks

2

Content specification

12.6 wks

Mon 2/18/19

Wed 5/15/19

0 wks

11

 Software

6 wks

Mon 2/18/19

Wed 5/15/19

Designer, Developer, Project Lead, Project Manager, Software Engineer, System Analyst

2

0 wks

12

 Hardware

5 wks

Fri 3/15/19

Thu 5/9/19

Project Lead, Project Manager[0%], Software Engineer, System Analyst

3

9.8 wks

13

 Market research

2 wks

Mon 3/25/19

Fri 4/5/19

Project Lead, Project Manager, Market Researcher, System Analyst

4

0 wks

3

Design

18.2 wks

Thu 5/9/19

Fri 9/13/19

0.4 wks

21

 User interface

7 wks

Thu 5/16/19

Thu 9/5/19

Designer, Developer, Software Engineer, System Analyst

11

0 wks

22

 Functionality

3 wks

Mon 7/1/19

Fri 7/19/19

Developer, Project Manager, Software Engineer, System Analyst, Tester

11,51

0 wks

23

 Battery

2 wks

Thu 6/20/19

Wed 7/3/19

Project Lead

12

9.8 wks

24

 Circuits

8 wks

Mon 7/22/19

Fri 9/13/19

Designer, Software Engineer, System Analyst, Tester

12,22

0 wks

25

 Display

3 wks

Fri 5/10/19

Tue 6/4/19

Project Manager, Software Engineer, System Analyst

12

10 wks

26

 Outer cover

6 wks

Thu 5/9/19

Thu 6/20/19

Market Researcher, Project Lead, Project Manager, Software Engineer

12

12.6 wks

27

 Camera

2 wks

Mon 7/22/19

Fri 8/2/19

Developer

11,12,51

4 wks

4

Implementation

21.6 wks

Tue 6/4/19

Fri 11/1/19

3 wks

31

 User interface

4 wks

Mon 9/16/19

Fri 10/25/19

Designer, Developer, Software Engineer, System Analyst

21,52

0 wks

32

 Functionality

4 wks

Fri 7/19/19

Mon 9/16/19

Designer, Developer, Software Engineer

22

5.8 wks

33

 Battery

2 wks

Thu 7/4/19

Mon 8/26/19

Project Lead, Project Manager

23

9.8 wks

34

 Circuits

7 wks

Mon 9/16/19

Fri 11/1/19

Designer, Developer, Market Researcher, Software Engineer, System Analyst

24

0 wks

35

 Display

5 wks

Tue 6/4/19

Fri 8/23/19

Project Manager, Software Engineer, System Analyst

25

10 wks

36

 Outer cover

5 wks

Fri 6/21/19

Tue 8/27/19

Market Researcher, Project Lead, Project Manager, Software Engineer

26

12.6 wks

5

Integration

10 wks

Mon 10/28/19

Fri 1/3/20

0 wks

41

 Software

4 wks

Mon 10/28/19

Fri 11/22/19

Designer, Developer, Market Researcher, Project Manager, Software Engineer, System Analyst

31,32,53

0 wks

42

 Hardware

3 wks

Mon 11/4/19

Fri 11/22/19

Developer, Software Engineer, System Analyst

33,34,35,53

0 wks

43

 Entire product

1 wk

Mon 11/25/19

Fri 11/29/19

Developer, Market Researcher, Project Lead, Project Manager, Software Engineer, System Analyst

36,41,42

0 wks

44

 Testing

5 wks

Mon 12/2/19

Fri 1/3/20

Software Engineer, System Analyst, Tester

43

0 wks

6

Subcontracting

25 wks

Mon 4/8/19

Fri 9/27/19

0 wks

51

 Market research (implementation)

12 wks

Mon 4/8/19

Fri 6/28/19

13

0 wks

52

 Games (design & implementation)

5 wks

Mon 7/1/19

Fri 8/2/19

11,51

4.8 wks

53

 Camera (implementation)

8 wks

Mon 8/5/19

Fri 9/27/19

27

4 wks

The critical path is sequence of the project stages determine minimum time required to complete the entire project work.

Figure 2: Critical path

From the above diagram, it is identified that the critical path is the shortest possible duration for the project which is highlighted in red.

Critical path activities = 1-2-3-4-13-22-24-34-42-43-44-51

= (3+5+4+1+2+3+8+7+3+1+5+12) weeks

= 54 weeks

Therefore, 54 weeks is the shortest possible duration for the project.

Gantt chart is the graphical method to demonstrate the development of the project work (Fuller et al. 2017). The tasks of the project plan are complex and it is dependent on each other which are shown in the diagram. With the project management tool such as Gantt chart, the sub-tasks of each project activities are viewed graphically.

Figure 3: Gantt chart

The remaining work is the amount of work in terms of the time unit that is left for completed on the project tasks.

Figure 4: Resource Histogram

Name

Start

Finish

Remaining Work

Project Manager

Mon 12/24/18

Fri 12/6/19

1,400 hrs

Developer

Mon 12/24/18

Fri 12/6/19

1,760 hrs

Software Engineer

Mon 12/24/18

Fri 1/10/20

2,120 hrs

Market Researcher

Mon 12/24/18

Fri 12/6/19

1,040 hrs

Tester

Mon 7/1/19

Fri 1/10/20

640 hrs

System Analyst

Mon 12/24/18

Fri 1/10/20

2,200 hrs

Designer

Mon 2/18/19

Fri 11/8/19

1,160 hrs

Project Lead

Mon 12/24/18

Fri 12/6/19

1,040 hrs

According to the study of Harrison and Lock (2017), in order to estimate the human resources for the project plan, it is estimated that there are total of 10 staffs selected at any one time to work into the project. The resources are level as per the limitation into the project work. It is also noticed that the tasks are not broken into pieces and not conducted for long period of time. The new Gantt chart for the project is shown along with the resource usage which is described in new resource diagram, then it will describe the shortest possible duration for the project plan as:

WBS

Task Name

Duration

Start

Finish

0

New hybrid handheld game console project

55 wks

Mon 12/24/18

Fri 1/10/20

1

   Requirements specification

13 wks

Mon 12/24/18

Fri 3/22/19

1

      Entire product

3 wks

Mon 12/24/18

Fri 1/11/19

2

      Software

5 wks

Mon 1/14/19

Fri 2/15/19

3

      Hardware

4 wks

Mon 2/18/19

Fri 3/15/19

4

      Market research

1 wk

Mon 3/18/19

Fri 3/22/19

2

   Content specification

11 wks

Fri 2/15/19

Fri 5/3/19

11

      Software

6 wks

Fri 2/15/19

Fri 3/29/19

12

      Hardware

5 wks

Mon 4/1/19

Fri 5/3/19

13

      Market research

2 wks

Mon 3/25/19

Fri 4/5/19

3

   Design

24 wks

Mon 4/1/19

Fri 9/13/19

21

      User interface

7 wks

Mon 4/1/19

Fri 5/17/19

22

      Functionality

3 wks

Mon 7/1/19

Fri 7/19/19

23

      Battery

2 wks

Mon 6/3/19

Fri 6/14/19

24

      Circuits

8 wks

Mon 7/22/19

Fri 9/13/19

25

      Display

3 wks

Mon 5/6/19

Fri 5/24/19

26

      Outer cover

6 wks

Mon 5/6/19

Fri 6/14/19

27

      Camera

2 wks

Mon 7/22/19

Fri 8/2/19

4

   Implementation

24 wks

Mon 5/27/19

Fri 11/8/19

31

      User interface

4 wks

Mon 9/2/19

Fri 9/27/19

32

      Functionality

4 wks

Fri 7/19/19

Fri 8/30/19

33

      Battery

2 wks

Mon 6/17/19

Fri 6/28/19

34

      Circuits

7 wks

Mon 9/16/19

Fri 11/8/19

35

      Display

5 wks

Mon 5/27/19

Fri 6/28/19

36

      Outer cover

5 wks

Fri 6/14/19

Fri 7/19/19

5

   Integration

15 wks

Mon 9/30/19

Fri 1/10/20

41

      Software

4 wks

Mon 9/30/19

Fri 10/25/19

42

      Hardware

3 wks

Mon 11/11/19

Fri 11/29/19

43

      Entire product

1 wk

Mon 12/2/19

Fri 12/6/19

44

      Testing

5 wks

Mon 12/9/19

Fri 1/10/20

6

   Subcontracting

25 wks

Mon 4/8/19

Fri 9/27/19

51

      Market research (implementation)

12 wks

Mon 4/8/19

Fri 6/28/19

52

      Games (design & implementation)

5 wks

Mon 7/1/19

Fri 8/2/19

53

      Camera (implementation)

8 wks

Mon 8/5/19

Fri 9/27/19

Figure 5: Gantt chart

Problem 1: Activity-on-node network

Figure 6: Updated resource diagram

The critical path of the new project plan is:

= 1-2-3-4-13-22-24-34-42-43-44-51

= (3+5+4+1+2+3+8+7+3+1+5+12) weeks

= 54 weeks, possible shortest duration of the project.

Therefore, it is seen that the duration of entire project is increased due to resource constraints.

Yes, the resource constraints can change perception of the critically of the project activities in new Gantt chart. Delay in the critical path activities will cause delay in the entire project work. Perceptions present way people become aware of other people’s concerns (Kerzner 2017). Therefore, the critical projects are crucial perception for the project manager.

In order to overcome with the resource constraints in the project, following recommendations are suggested to the project manager as:

Resource planning: A proper resource planning is required in the project before the activity is required to have resources assigned to the project activities as per their availability. Therefore, proper resource estimation is done to assign the resources to each project activities in activity list.

Hire of more resources: As per division of the project activities for conducting the project work, the HR manager should hire resources as per the tasks. The resources are selected based on their skills and expertise.

Conclusion

It is concluded that the report is relevant to the project management bodies of knowledge which is an evaluation tool used to focus as well as measure management of change within project domains. The project manager ensures that all terms of project are being addressed. The project management tool is used to handle change dynamics will add towards supporting as well as leveraging individual capital of organization in awareness with familiar goals as well as improved the development deliverables.

From this report, it is learnt that monitoring and controlling of project plan is required to keep track of the project. The project management team can understand reasons for the project and the factors which can influence the project activities. There is also support plus participation of the project stakeholders to ensure controlled development of project plan. This report addresses development of activity on node diagram and analyzes corrective actions to determine the project schedule. We have leant about the critical path method which measures the longest path of the developed project activities to complete the project work. When any of the project activity is delayed, then it impacts the considered project completion time. Understanding of the critical path permits the project manager to decide which project schedule activities are flexible and those are the activities which are not on critical path. By observing the network diagram, the project manager can decide the float or slack. It is sum of time that the calendar activities can stoppage without reasoning any delay to the starting date of the tasks or project completion time. By addition of resource limits, the result leads that the critical path is longer. Resource forced critical path is termed as critical chain.  

The network diagram is schematic displays of the project schedule tasks along with interdependencies among the project activities. The graphical view of the project related activities will convey vital schedule needed to examine as well as adjust the project schedule (Larson and Gray 2015). The network diagram visually expresses the critical path which allows the project manager to give priority to the project tasks moreover get proper actions to meet with scheduled project deadlines.

Forward pass calculation

Activity

Time

EST

EFT

A

5

0

5

B

7

5

12

C

2

5

7

D

12

12

24

E

20

12

32

F

4

7

11

G

11

7

18

H

8

24

32

I

6

32

38

J

3

32

35

K

9

11

20

L

1

32

33

M

14

35

49

N

19

49

68

Activity

Time

EST

EFT

LST

LFT

A

5

0

5

0

5

B

7

5

12

5

12

C

2

5

7

34

36

D

12

12

24

28

40

E

20

12

32

12

32

F

4

7

11

36

40

G

11

7

18

38

49

H

8

24

32

40

48

I

6

32

38

43

49

J

3

32

35

32

35

K

9

11

20

40

49

L

1

32

33

48

49

M

14

35

49

35

49

N

19

49

68

49

68

Activity

Time

EST

EFT

LST

LFT

Slack

Criticality

A

5

0

5

0

5

0

**

B

7

5

12

5

12

0

**

C

2

5

7

34

36

29

D

12

12

24

28

40

16

E

20

12

32

12

32

0

**

F

4

7

11

36

40

29

G

11

7

18

38

49

31

H

8

24

32

40

48

16

I

6

32

38

43

49

11

J

3

32

35

32

35

0

**

K

9

11

20

40

49

29

L

1

32

33

48

49

16

M

14

35

49

35

49

0

**

N

19

49

68

49

68

0

**

From the above table, it is seen that the critical path of the project is:

= A-B-E-J-M-N

= (5+7+20+3+14+19) weeks

= 68 weeks.

References

Fuller, M.A., Valacich, J.S., George, J.F. and Schneider, C., 2017. Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.

Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.

Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Larson, E.W. and Gray, C.F., 2015. A Guide to the Project Management Body of Knowledge: PMBOK (®) Guide. Project Management Institute.

Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.

Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), pp.1382-1394.

Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.

Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392.

Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.

Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.

Lientz, B. and Rea, K., 2016. Breakthrough technology project management. Routledge.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Ramazani, J. and Jergeas, G., 2015. Project managers and the journey from good to great: The benefits of investment in project management training and education. International Journal of Project Management, 33(1), pp.41-52.

Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.

Todorovi?, M.L., Petrovi?, D.?., Mihi?, M.M., Obradovi?, V.L. and Bushuyev, S.D., 2015. Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), pp.772-783.

Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.