McGrade Luxury House: Architectural Plan Review And Construction Details

Building Segments

McGrade luxury house is another facility that comprise of three building segment that are isolated by slab floors. The basement is meant for parking of vehicle and furthermore it has a segment of support of the lift. The ground floor had three bedrooms, study room, rumpus room, laundry, washrooms and latrine in every room and store room, lastly the first floor that have the replica of ground floor.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

During the architectural plan review the following will be considered;

Verification of the loads imposed on the structure due to dead load, fixed equipment, storage, live load.

Comment;

 They are all coordinated with structural assumptions.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Verification of adequacy of non-structural components.

− Ceilings and soffits

Comment;

 Their connections resist vertical and lateral loads

− Equipment, storage racks, cabinets and casework

 Comment;

 Their connections resist vertical and lateral

− Parapets, architectural ornamentation and appendages

 Comment;

 Their connections resist vertical and lateral

Verification of architectural dimensions (thickness of walls, depth of roof structure, etc.).

Comment;

Their coordination are well fitted

Verification of the wood.

Comment

They are all protected against moisture, decay, and termites

Verification of the enclosed spaces

Comment;

 They are well adequately ventilated.

Verification of the adequate roof drainage has been provided.

Comment;

They are all provided   

The building envelope will contain materials that incorporate block around the base of the working up to a precast banding. The banding will fill in as a change to larger than average brick work boards. Aluminum Cladding is additionally utilized for outside dividers and shade spaces. Customer facing facade style Glass Walls will likewise be utilized all through the McGrade luxury house.

One of the principle highlights of the building will be its Metal Canopy that stretches out finished the Main Entry. 

The total project is booked to take around 530 Days. Substructure is anticipated to keep going for around 165 days, superstructure will take around 130 days and the rough in and complete course of events is around 140 days. Building closeout incorporates testing for LEED point confirmation and other testing and parities, and also last punch list work. Final completion is relied upon to be on twentieth December 2018. See Gantt diagram Summary Schedule. 

The soil being unstable will expect geopiers to be built under footings to make a high load bearing capacity. Whatever is left of the site and sheds will utilize spread footings.

The area of pool on the back side of the house territory will include the establishment of sheeting and shoring, a mud tangle, and unique water-sealing of the Pool Structure all around.

Architectural Plan Review

Fundamentally the house will be built in three portioned segments of floors.

The Substructure and Superstructure will both take after comparative grouping ways. The basement Section and core of the building will always lead followed by the ground floor and afterward the first floor. By sectioning the calendar all through the procedure teams will have the capacity to be of small sizes and more beneficial, if different exchanges have officially moved out of a specific zone before the following group beginning its work. There is however various exchanges that will require tight joint effort to make progress on this undertaking. The essential illustration being, the Electrical Contractor and Masonry Contractor the same number of square dividers should be roughed in while being built. The Rough-in and finish schedule will follow a similar sequence by starting in the basement, progressing to the ground floor and then finishing in the first floor of building. 

Normally in the Australia region the favored strategy for development is cast in place concrete. It is intriguing that the basic framework is mostly standard steel construction. With building height not being a plan constraint, in regard to augmenting number of floors this may have figured into the technique method chosen.

The site permits restricted nearby stopping which is accessible. The encompassing zone is generally private and road stopping will give adequate parking spots amid development.

Numerous construction recycling organizations are accessible to the Queensland area, from aggregate site recycling to arranging and hauling services.

The soil bearing capacity does not require much more than the use of geo-piers in specific areas. Spread footings are adequate in many territories and for segregated structures around sports facilities. 

Table 1: Square foot estimates summary

Construction cost

Source

Construction cost per square meter

$3,994, 992

D4 cost estimating

$170.92

$4, 120, 400

R.S mean

$213.45

$8,000,000

Actual

$385.74

The project task has a financial plan of $10 million and building expense of $8 million. The genuine building cost per square meter was ascertained to be $386. In Table 1, a correlation with the parametric gauge made utilizing D4 Cost Estimating can be seen; the evaluations made in this report give off an impression of being low.

The genuine building cost considers the numerous civilities and offices made for McGrade extravagance house. In D4 it is entirely taking a gander at square meter and a comparable size of the building.

The gauge utilizing Cost works (RS Means) has brought about a gauge of $4.1 million. The amendments made to the base square meter cost include: changing in accordance with proper story tallness and edge and also some extra civilities. The substantial contrasts can be represented in the distinctions in the plan of the task contrasted with different offices. RS Means square meter cost information can’t represent the numerous pleasantries incorporated into the real development expenses of McGrade luxury house. 

Verification of Loads and Components

Table 2: MEP and structural cost estimates summary *Estimated Values

System

System cost

% total

Cost per square meter

Mechanical

$5,000, 000*

16

$60.50

Electrical

$3,000,000

12

$48.67

Structure

$2,000,000*

4

$16.75

The McGrade luxury house is presently anticipated to meet LEED Gold under LEED for Program. This rating will be accomplished by concentrating on Indoor Air Quality and Optimizing Energy Performance. A huge segment of the rooftop (more than 40%) will be broad green rooftop gardens, while the rest of the territories will be an exceptionally intelligent EPDM roofing material. Summary of the LEED can be seen below in Table 3. 

Table 3: LEED 2009 New construction and major renovation

LEED 2009 New construction and major renovation

Categories

points planned to be earned

yes

may be

No

maintainable site

15

2

6

Water Efficiency

10

3

0

Atmosphere and Energy

11

0

19

Resources and materials

7

1

5

Quality Indoor Environmental

15

0

3

Design Process and Innovation

3

1

2

Credits of Regional Priority

0

0

0

Total

61

7

35

gold = 60 to 79 points

The analysis begins with an examination concerning the green rooftop. Where the properties of the green rooftop examination included: cost, warm effectiveness, storm water stockpiling limit, weight, and construction span. Warm properties of the green rooftop framework are extremely intricate and will require cautious and innovative contemplations. Construction term for the rooftop framework can be diminished strikingly. At last, cost will be computed with changes and effects of alternate frameworks to decide the feasibility of taking out the green rooftop. To finish up this analysis taking LEED affirmation, Value Engineering and Schedule Reduction into thought will decide the dangers and openings related with Optimizing Value Engineering. 

Green rooftops give numerous focal points and burdens that should all be considered when choosing on the off chance that it is a reasonable choice for a material gathering. A couple of favorable circumstances to green rooftops are: storm water administration properties, goes about as a warm mass, capacity to clean the air and conceivable long haul vitality funds. A few inconveniences are: high introductory costs, expanded rooftop dead loads, support concerns and exorbitant repairs if required. 

The drawings or sheets listed on the cover or index sheet

This drawing, page of specifications/calculations have been set up by other plan experts or advisors who are authorized and additionally approved to get ready such illustrations in this state. It has been analyzed by me for: 1) outline plan and seems to meet the suitable prerequisites of Title 24, California Code of Regulations and the task determinations arranged by me, and

2) Coordination with my plans and determinations and is adequate for joining into the development of this undertaking.

The Statement of General Conformance “might not be understood as calming me of my rights, obligations, and duties under Sections 17302 and 81138 of the Education Code and Sections

4-336, 4-341 and 4-344” of Title 24, Part 1. (Title 24, Part 1, Section 4-317 (b))

I find that:       All drawings or sheets listed on the cover or index sheet

                       This drawing or page

        is/are in general conformance with the                                        project design, and

      has/have been coordinated with the project      plans and specifications.

       is/are in general conformance with the project design intent, and

       has/have been coordinated with the project plans and specifications.

Signature

Date

Signature

Date

Architect or Engineer designated to be in

general responsible charge

Architect or Engineer delegated responsibility

for this portion of the work

Print Name

Print Name

License Number 342

Expiration Date 02/02/2019

License Number

Expiration Date

Building Envelope

Time Schedules of activities  

Table 4: Time schedule of activities

Activities number

Descriptions

Duration

Early  start

Early finish

Late start

Late finish

Total float

Free float

5

PROJECT NOTICE APPROVAL

3

26 may 2018

28 may 2018

26 may 2018

28 may 2018

0

0

10

DEVELOP WORK PLAN

7

29 may 2018

6 June 2018

29 may 2018

6 June 2018

0

0

15

FORM PROJECT TEAM

5

9 June 2018

13 June 2018

9 June 2018

13 June 2018

0

0

20

DESIGN CONTRACTOR’S WORK

2

16 June 2018

17 June 2018

25 June 2018

26 June 2018

7

0

25

IN-HOUSF: DESIGN WORK

3

16 June 2018

18 June 2018

16 June 2018

18 June 2018

0

0

30

DESIGN BRIEFING MEETING

1

18 June 2018

18 June 2018

27 June 2018

27 June 2018

7

0

35

PROJECT SITE-WORK DESIGN

1

19 June 2018

19 June 2018

25 June 2018

25 June 2018

4

0

40

ON-SITE UTILITIES DESIGN

1

19 June 2018

19 June 2018

7 Aug 2018

7 Aug 2018

35

0

45

A/E DESIGN BUILDING A

1

19 June 2018

19 June 2018

19 June 2018

19 June 2018

0

0

50

FLOOR PLAN GROUND

10

20 June 2018

3 July 2018

30 June 2018

11 June 2018

7

0

55

SITE GRADING PLAN

12

20 June 2018

7 July 2018

26 June 2018

11 June 2018

4

0

60

STORM-WATER DESIGN

10

20 June 2018

3 July 2018

8 Aug 2018

21 Aug 2018

35

0

65

FLOOR PLAN FIRST FLOOR

15

20 June 2018

10 July 2018

20 June 2018

10 June 2018

0

0

70

FOUND/STRUCT OF THE BUILDING

45

3 July 2018

3 Sep 2018

22 June 2018

22 Sep 2018

13

0

75

ARCH FINISHES OF THE BUILDING

30

3 July 2018

13 Aug 2018

12 Aug 2018

22 Sep 2018

28

15

80

SANITARY SEWER DESIGN

21

10 July 2018

1 Aug  2018

10 July 2018

1 Aug 2018

0

0

85

DOMESTIC WATER SYSTEM

7

5 Sep 2018

12 Sep 2018

5 Sep 2018

12 Sep 2018

0

0

90

PLUMBING.

10

2 Oct 2018

12 Oct 2018

2 Oct 2018

12 Oct 2018

0

0

95

FINAL INSPECTION & APPROVAL

3

3 Dec 2018

6 Dec 2018

3 Dec 2018

6 Dec 2018

0

0

Table 5: Cost of schedules of activities

Activities number

Descriptions

Duration

Cost

5

APPROVAL OF PROJECT NOTICE

3

$500

10

 WORK PLAN DEVELOPMENT

7

$1200

15

FORMATION OF PROJECT TEAM

5

$850

20

CONTRACTOR’S WORK DESIGN

2

$3000

25

IN-HOUSF: DESIGN WORK

3

$1500

30

BRIF MEETING ON DESIGN

1

$1200

35

WORK DESIGN ON PROJECT SITE

1

$1400

40

ON-SITE UTILITIES DESIGN

1

$1200

45

A/E DESIGN BUILDING A

1

$1500

50

FLOOR PLAN GROUND

10

$9000

55

PLAN OF SITE GRADING

12

$14000

60

STORM-WATER DESIGN

10

$2000

65

FIRST FLOOR FLOOR PLAN

15

$26000

70

FOUND/STRUCT OF THE BUILDING

45

$31200

75

ARCH FINISHES OF THE BUILDING

30

$49000

80

DESIGN OF SANITARY SEWER

21

$12000

85

DOMESTIC WATER SYSTEM

7

$9000

90

PLUMBING.

10

$28500

95

FINAL INSPECTION & APPROVAL

3

$3500

Table 6: list of activities Project: 060608/WBS-1 Pacific Motorway

CONCEPT PHASE

Project Management

Appoint Project Manager

Community Engagement

Project Proposal

Determination of  a functional Necessities and Scope

Project Proposal production

Development of Options Analysis and Recommendations

Develop Concept Planning Brief

Procure Concept Planning Consultant

Produce Options Analysis and Recommendations

Recommend Preferred Option

Approved Recommended Option

Develop Preferred Option

Business Case

Review Risk Register and Project Estimate

Produce Business Case

Financial Approval

DEVELOPMENT PHASE

Project Management

Project Management General

Development Phase

Prepare Design Brief

Community Engagement Development Phase

Preliminary Design

Procure Preliminary Design Consultants

Produce Preliminary Design

Detailed Design

Procure Detailed Design Consultants

Obtain Legislative Approvals and Permits

Produce Detailed Design

Contract Documents

Produce Contract Documents

Pre-tender Financial Approval

Preliminary Works

Obtain Approval for Preliminary Works

Acquire Right of Way

Procure Public Utility Plant (PUP) Services

Procurement

Engage Contract Administrator

Procure Contractor

Contract Financial Approval

Contract Award

IMPLEMENTATION PHASE

Project Management

Project Management (General)

Implementation Phase

Community Engagement Implementation Phase

Contract Administration

Practical Completion Certificate

Construction

Principal’s Responsibility

Official Opening

FINALISATION PHASE

Project Management

Project Management (General)

Finalization Phase

Defects Liability Period

Final Certificate

Community Engagement – Finalisation Phase

Complete Project Handover Report

Evaluate Project Performance

Post Implementation Review

Close Out Consultation

Statement and Construction Project Budget approved.

Facility Budget

Site-Work.. …………………. $522,400

Grading

Paving

Landscaped

On-Site Utilities ………………. $1 73,700

Storm water

Sanitary Sewer

Domestic Water

Underground Electrical

Natural Gas

Maintenance Building……….. .$1,083,600

Architectural

Structural

Electrical

Plumbing

Heat & Air

Project Management………….. $19,350

Clerical

Procurement . . . . . . . . . . . . . . . . . . . . . $1 57,000

Procurement . . . . . . . . . . . . . . . . . . . . . $1 57,000

Crane

Elevators

Construction Bids

Total Directs = $3,053,150

Contingency ………………… $1 50,000

Total Approved Budget = $3,203,150  

A/E Building Architectural

Dan Milter plot plan

Architectural floor plan

Plot plan sanitary sewer site improvement

Floor plan   – fencing structural

Electricity   – landscaping foundation

Structural Water paving

Foundation Domestic   – sub base mechanical

Fire protection    concrete plumbing

Mechanical Telephone                   – parking /walk heat and air

Plumbing Domestic electrical

Heat and air Security aggregate finish 

Electrical

Finishes

Work package

Title: Maintenance Building

WBS: 20021

Scope

Required scope of work: Architectural

Service to be provided: floor plan drawing

Services not included in this Work Package, but included in another work package:

House units drawing plan

Services not included in this Work Package, but will be performed by:

Budget 

Table 7: showing Budget      

Personnel assign to the job

Work – hours

$-cost

CBS code Acct

Computer services

Type

Hour

$-cost

Fredrick James

10

$20

2345

Typing and printing

6

$5

Schedule 

Table 8: Schedule 

OBS

Code

Task of Work

Accountable person

Date to start

Date to end

2376

Floor plan drawing

Fredrick James

16 June 2018

18 June 2018

Work package: start date:  16 June 2018           end date: 16 June 2018 

Additional comment: The work must be completed as agreed in all terms and conditions 

Prepared by:    Peter Kelvin                             Date: 02 march 2018 

Approved by:     David Jones                            Date: 05 march 2018 

Critical Path Method (CPM) diagram for service facility project

Bored excavation for 300mm diameter piers

Table 9: Total volume is calculated by considering bulking factor of soil

Item

Particulars

Unit

Quantity

Rate

$Cost

1

Bored excavation volume for 53 Ø300mm and 2.5m deep piers

Cross sectional area of pier = πr2 = π x 0.152 = 0.07m2

Volume of pier = cross sectional area x depth

= 0.07 x 2.5 = 0.18m3

Volume of 53 piers = 0.18m3 x 53 = 9.54m3

Assume bulking factor of 1.4 (clay soil), total volume of soil material to be excavated for boring of piers = 1.4 x 9.54 = 13.6m3 

m3

14

$53571.43

$750,000

A total of 53 53 Ø300mm and 2.5m deep pier bores shall be excavated. For all the 53 piers, a total volume of about 14m3 of soil material will be excavated for the piers to be bored.

Table 10: Bulk excavation for general site preparation

Item

Particulars

Unit

Quantity

Rate

$ Cost

2

Bulk excavation

m3

150

$3,533.33

$530,000

Overall bulk area of excavation (plus working space) = (12.83 + 4.08 + 2.00) x (11.87 + 2.00)

= 18.91 x 13.87 = 262.28

Estimated depths at corners: NE – 0.69m, NW – 0.55m, SE – 0.50 and SW – 0.45)

Average depth = (0.690 + 0.54 + 0.45 + 0.40)/4 = 0.55m

Volume of bulk excavation = area x depth

= 262.28m2 x 0.55m = 144.25

Assume that only one side is battered = 18.91m x 1.0m wide x 0.55m = 10.40m3

Since battering is done at 45 degrees, battered volume is = 0.5 x 10.40 = 5.20

Total volume of bulk excavation = 144.25 + 5.20 = 149.45

A total of 150m3 of shall be excavated from the site during general preparation of the site. This bulk volume includes working space, which extends outside the building towards the boundary by 1m. The longest side of the building shall also be battered at an angle of 45 degrees and a width of 1m from the building. The total bulk volume of 150m3 to be excavated includes the actual site of the house, working space and battered volume. The subcontractor has to use this value to determine the most suitable equipment to use for bulk excavation and if the excavated material will have to be cart away.

Project Timeline and Methodology

N25 concrete for the ground slab (beams, patio slab and pad footings)

Thickness of slab = 150mm = 0.15m

Thickness of beam = 450mm = 0.35m

Width of beam = 100mm = 0.1m

Table 11: N25 concrete for the ground slab (beams, patio slab and pad footings

Item

Particulars

Unit

Quantity

Rate

$      C

3

N25 Concrete for ground slab

m3

Slab on ground = length x width x slab thickness

= 12.83m x 11.87m x 0.15m = 22.84

m3

23

Patio slab = length x width x thickness

= 6.35m x 1.67m x 0.15m = 1.59  

m3

2

Family room = length x width x thickness

= 5.51m x 4.08m x 0.15m = 3.37

m3

4

Beams on slab = total length of beams x width of beam x depth of beam

= 82.82m x 0.1m x 0.45m = 3.73    

m3

4

Pad Footings

Area = 10(1.2 x 0.9) + (0.35 x 2.4)

= 10.80 + 0.84 = 11.64m2

Volume = area x depth

= 11.64 x 0.35 = 4.074

m3

5

Total

m3

38

$22,894.74

$870,000

A total volume of 38m3 of N25 concrete shall be required for the whole ground slab, including beams, patio slab and pad footings but excluding piers. Depending on the mix design recommended by the engineer, it noes becomes easier to determine the volume of concrete ingredients (concrete, coarse and fine aggregates and sand) needed for the ground slab.  

SL72 reinforcing mesh for the ground slabs

Table 12: SL72 reinforcing mesh for the ground slabs

Item

Particulars

Unit

Quantity

Rate

$      C

4

Number of SL72 Reinforcing Mesh Sheets

4 (a)

Area of ground slab to be reinforced with mesh (including 50mm cover)

= length x width = 11.98m x 11.02m

= 132.02m2

Area of family room to be reinforced with mesh

= length x width = 4.66m x 3.68m = 17.15m2

Total area of slab to be covered = 132.02 + 17.15 = 149.17m2 

m2

150

$6,000

$900,000

4 (b)

Number of sheets = total area of slab/ effective area of SL72

Total area of slab to be reinforced with SL72 mesh = 150m2

Effective area of SL72 sheet = 5.8m x 2.2m = 12.76m2 

Number of SL reinforcing mesh sheets = 150/12.76 = 11.76

No

12

Summary:

The total area of slab that requires to be covered by the SL72 reinforcing mesh is 150m2. Based on this area (and putting into consideration the required overlap length and cover at the edges), the number of 6.0m x 2.4m with 400mm lap SL72 reinforcing sheets required to complete the slab is 12.

Table 14: Lengths of SL12TM for ground slab construction

Item

Particulars

Unit

Quantity

Rate

$      C

5

Length and number of SL12TM Trench Mesh

 5 (a)

Length of trench mesh (including 200mm lap)

= length of one trench x number of trenches

= 13.23m x 3 = 39.69m

= length of one trench x number of trenches

= 12.27m x 3 = 36.81m

= length of one trench x number of trenches

= 4.48m x 2 = 8.96m

= length of one trench x number of trenches

= 5.91m x 1 = 5.91m

Total length of trench mesh = 39.69 + 36.81 + 8.96 + 5.91 = 91.37

m

92

$13,043.48

$1,200,000

5 (b)

Number of SL12TM trench mesh

16 sheets

= Length of trenches/length of trench sheets

= 92/6 = 15.33

No

16

The total length of SL12TM trench mesh needed for ground lab (including overlap of 200mm at each end) is 92m. Since each trench measure comes in 6m lengths, the number of lengths of SL12TM trench mesh needed is 16. Therefore the contractor will have to supply 16 sheets of 6m long SL12TM trench mesh.

Table 15: Structural steel

Item

Particulars

Unit

Quantity

Rate

$      C

6

Structural steel

tonnes

1.78

$1,432,584.3

$2,550,000

B1

Weight = 25.7kg/m x 12.83m = 329.73kg

B2

Weight = 32kg/m x 12.83m = 410.56kg

B3

Weight = 14kg/m x 11.87m = 166.18kg

B4

Weight = 14kg/m x 11.87m = 166.18kg

B6

Weight = 14kg/m x 11.87m = 166.18kg

B5

Weight = 31.6kg/m x 12.83m = 405.43kg

L1

Weight = 14.6kg/m x 4.08m = 59.57kg

L2

Weight = 14.6kg/m x 5.51m = 80.45kg

Total weight = 329.73 + 410.56 + 166.18 + 166.18 + 166.18 + 405.43 + 59.57 + 80.45 = 1784.28kg

Summary:

The total weight of structural steel needed for the project is 1.78 tonnes. 

Plasterboard

Table 16: Plasterboard

Item

Particulars

Unit

Quantity

Rate

$      C

7

Plasterboard

 7 (a)

Area of plasterboard

Assume that the height of plasterboard wall is 2.4m

Area of wall = length of wall x height of wall

A1 = 11.93m x 2.4m = 28.63m2

A2 = 11.93m x 2.4m = 28.63m2

A3 = 11.93m x 2.4m = 28.63m2

A4 = 11.93m x 2.4m = 28.63m2

A5 = 10.97m x 2.4m = 26.33m2

A6 = 10.97m x 2.4m = 26.33m2

A7 = 10.97m x 2.4m = 26.33m2

A8 = 10.97m x 2.4m = 26.33m2

A9 = 3.63m x 2.4m = 8.71m2

A10 = 3.63m x 2.4m = 8.71m2

A11 = 4.61m x 2.4m = 11.06m2

A12 = 4.61m x 2.4m = 11.06m2

Total area of walls = 4(28.63) + 4(26.33) + 2(8.71) + 2(11.06) = 259.38m2

Deduct area of doors and windows

Total area of doors = 5(2m x 0.9m) = 9.00m2 

Area of windows = 6(1.2m x 0.8m) = 5.76m2

Total area of doors and windows = 9.00 + 5.76 = 14.76m2

Net measure = 259.38 – 14.76 = 244.62m2

m2

245

$1,632.7

$400,000

7 (b)

Number of plasterboard sheets

The selected size of plasterboard sheets is 1200mm wide and 2400mm long

Area of one plasterboard sheet = 1.2m x 2.4m = 2.88m2

Number of sheets = net measure of wall/area of one sheet

= 245m2/2.88m2 =85.07

No

86

Summary:

The total area of wall that will be covered with plasterboard is 245m2 and a total of 86 plasterboard sheets measuring 1200mm wide and 2400mm long shall be required for the project.

66x18mm finished DAR primed pine skirting

Table 17: 66x18mm finished DAR primed pine skirting

Item

Particulars

Unit

Quantity

Rate

$      C

8

66x18mm finished DAR primed pine skirting

8 (a)

Length of skirting

L1 = 11.93m

L2 = 11.93m

L3 = 11.93m

L4 = 11.93m

L5 = 10.97m

L6 = 10.97m

L7 = 10.97m

L8 = 10.97m

L9 = 3.63m

L10 = 3.63m

L11 = 4.61m

L12 = 4.61m

Total length of skirting = 4(11.93) + 4(10.97) + 2(3.63) + 2(4.61) = 108.08m

Plus 5% wastage

Total length of skirting (including wastage) = 1.05 x 108.08 = 113.48

m

114

$2,631.58

$300,000

8 (b)

Number of skirting lengths  

The selected length of 66x18mm finished DAR primed pine skirting is 2.7m

Number of skirting lengths = length of skirting/ selected length of skirting

L1: 11.93m/2.7m = 4.42 = 5 sheets

L2: 11.93m/2.7m = 4.42 = 5 sheets

L3: 11.93m/2.7m = 4.42 = 5 sheets

L4: 11.93m/2.7m = 4.42 = 5 sheets

L5: 10.97m/2.7m = 4.06 = 5 sheets

L6: 10.97m/2.7m = 4.06 = 5 sheets

L7: 10.97m/2.7m = 4.06 = 5 sheets

L8: 10.97m/2.7m = 4.06 = 5 sheets

L9: 3.63m/2.7m = 1.34 = 2 sheets

L10: 3.63m/2.7m = 1.34 = 2 sheets

L11: 4.61m/2.7m = 1.71 = 2 sheets

L12: 4.61m/2.7m = 1.71 = 2 sheets

Total sheets = 8(5) + 4(2) = 48

No

48

Summary:

The total length of skirting is 114m and a total of 48 lengths of 66x18mm finished DAR primed pine skirting measuring 2.7m long shall be required for the project. 

Table 18: Ceramic floor tiles

Item

Particulars

Unit

Quantity

Rate

$      C

9

Ceramic floor tiles

9 (a)

Amount of ceramic floor tiles

Family room = 4.08m x 5.51m = 22.48m2

Plus 10% wastage = 1.10 x 22.48m2 = 24.73m2 ≈ 25m2

Meals room = 2.43m x 4.68m = 11.37m2

Plus 10% wastage = 1.10 x 11.37m2 = 12.51m2 ≈ 13m2

Kitchen

Floor tiles: 4.59m x 6.11m = 28.04m2   

Plus 10% wastage = 1.10 x 28.04m2 = 30.85m2

Wall tiles (under cupboards) = 2(4.59m x 1.8m) + 2(6.11m x 1.8m) = 38.52m2

Plus 10% wastage = 1.10 x 38.52m2 = 42.37m2

Total kitchen = 30.85 + 42.37 = 73.22m2 ≈ 74m2

Foyer/stair area = 1.71m x 1.09m = 1.86m2

Plus 10% wastage = 1.10 x 1.86m2 = 2.05m2 ≈ 3m2 

Total = 25 + 13 + 74 + 3 = 115

m2

115

$6,956.52

$800,000

9 (b) (i)

Number of boxes of floor tiles

Number of boxes of floor tiles = area of floor tiles/1.2m2 = (25 + 13 + 31 + 3)/1.2 = 72m2/1.2m2 = 60

No

60

9 (b) (ii)

Number of boxes of wall tiles

Number of wall tiles = area of wall tiles/1.4m2 = 43m2/1.4m2 = 30.71

No

31

Summary:

A total area of 115m2 (including family room, meals room, kitchen and foyer/stair area) shall be tiled. 60 boxes of floor tiles and 31 boxes of wall tiles shall be required for the project.  

Table 19: External opening

Item

Particulars

Unit

Quantity

Rate

$cost

10

External opening

Door frames, windows and finishes

m2

672.5

$892.19

$600,000

Wrot mahogany

Rebated frame

200 mm * 50 mm = 0.2 m * 0.05 m = 0.01 m2

Number of frame = 3000

Quantity = 0.01 * 3000 = 30 m2

Architrave

 50 mm * 25 mm = 0.05 m * 0.025 m = 0.00125 m2

Total number = 1000

Quantity = 0.00125 * 1000 = 1.25 m2

Total area = 30 + 1.25 = 31.25

Number of doors = 22

Total area = 31. 25 m2 * 22 = 627.5 m2

Carpenter rate per hour = $45

Total time taken = 15 hours

Total labor cost = 15 hours * $45 = $675

Windows

Windows size = 1500 mm * 1500 mm = 2250000 mm2

Number of windows = 20

Total area = 20 * 2250000 mm2 = 45000000mm2 = 45 m2

Windows board

 125 mm * 25 mm = 3125 mm2

Curtain rod

25 mm diameter chrome curtain rod

20 mm diameter curtain

Number of curtain rod = 6

Fixing of curtain rod = 6 hours

Rate of fixing curtain rod per hour = $3

Total cost = 6 hours * $3 = $18

 

 Table 20: plumbing cost

Plumbing

Item particulars

Unit

Quantity

Rate

Cost

A       Plumbing work to Powder, Laundry, ensuite and Bathroom  areas including the supply and fixing of all fittings.                               

B          Supply prices from provided PC schedule                                               

 C        Labour constants per Rawlinson 2014                                                      

D       Toilet suites to areas as noted;                                                                      

No

4

$25,600

$102,400

                  Powder     – 1

                  Laundry     – 1

                  Ensuite      – 1

                  Bathroom – 1

                                    4

            Supply (PC)                               $600

            Labour 2.50 hrs @ $10,000/hr =  $25,600

                                                             $800                                                                       each WC pan and cistern

  E       Shower bases to areas as noted;                                                                     

No

3

$30,500

$91,500

                  Powder     – 1

                  Laundry     Nil

                  Ensuite      – 1

                  Bathroom – 1

                                      3

           Supply (PC)                               $500

         Labour 3.00 hrs @ $10,000/hr =  $30,000  

                                                        $30,500

Per shower base

F       Baths to areas as noted;                                                                                    

No

1

$20,750

$20,750

                    Bathroom -1

            Supply (PC)                                            $750

            Labour 2.00 hrs @ $10,000/hr =     $20,000

                                                            $20,750

Per bath

 Total

 $214,650

 Table 21: Drainage cost

Drainage  

Item particulars

Unit

Quantity

Rate

Cost

A       Drainage work to Powder, Laundry, ensuite and Bathroom  areas including the supply and fixing of all fittings.                               

B          Supply prices from provided PC schedule                                               

 C        Labour constants per Rawlinson 2014                                                      

D       Toilet suites to areas as noted;                                                                      

No

5

$50,600

$253,000

                  Powder     – 2

                  Laundry     – 1

                  Ensuite      – 1

                  Bathroom – 1

                                    5

            Supply (PC)                               $600

            Labour 5 hrs @ $10,000/hr =  $50,000

                                                          $50,600

  E       Shower bases to areas as noted;                                                                     

No

4

$30,500

$122,000

                  Powder     – 2

                  Laundry     Nil

                  Ensuite      – 1

                  Bathroom – 1

                                    4

           Supply (PC)                               $500

         Labour 3.00 hrs @ $10,000/hr =  $30,000  

                                                          $30,500

Per shower base

F       Baths to areas as noted;                                                                                    

No

1

$30,750

$30,750

                    Bathroom -1

            Supply (PC)                                  $750

            Labour 3.00 hrs @ $10,000/hr =     $30,000

                                                               $30,750

Per bath

 Total

 $405,750

 Table 22: electricity cost 

Electricity  

Item particulars

Unit

Quantity

Rate

Cost

A      Toilet suites to areas as noted;                                                                      

No

4

$30,600

$122,400

                  Powder     – 1

                  Laundry     – 1

                  Ensuite      – 1

                  Bathroom – 1

                                     4

            Supply (PC)                               $600

            Labour 3 hrs @ $10,000/hr =  $30,000

                                                        $30,600

  B       Shower bases to areas as noted;                                                                     

No

3

$30,500

$91,500

                  Powder     – 1

                  Laundry     Nil

                  Ensuite      – 1

                  Bathroom – 1

                                    3

           Supply (PC)                               $500

         Labour 3.00 hrs @ $10,000/hr =  $30,000

$30,500

Per shower base

C       Baths to areas as noted;                                                                                    

No

1

$20,750

$20,700

                    Bathroom -1

            Supply (PC)                                  $750

            Labour 2.00 hrs @ $10,000/hr =     $20,000

                                                               $20,750

Per bath

D Hot tub  areas as noted;                                                                     

 2

 $30,500

 $61,000

                  Ensuite      – 1

                  Bathroom – 1

3

           Supply (PC)                               $500

         Labour 3.00 hrs @ $10,000/hr =  $30,000

                                                        $30,500

E Tape ware areas as noted;                                                                     

No

3

$21,000

$63,000

                  Laundry     -1

                  Ensuite      – 1

                  Bathroom – 1

3

           Supply (PC)                               $1000

         Labour 2.00 hrs @ $10,000/hr =  $20,000  

                                                         $21,000

Vanity areas as noted;                                                                     

No

3

$20,000

$60,000

                  Laundry     -1

                  Ensuite      – 1

                  Bathroom – 1

3

           Supply (PC)                               $600

         Labour 3.00 hrs @ $10,000/hr =  $30,000  

                                                        $30,600

Total

418,600

The approximate total cost of the project of building McGrade luxury house is $10 million 

Table 23: Risk management plan for program delays

Sub risk:  Mean  and standard deviation

1 Shortage of skilful workers  4.58

SD = 3.61

2 Time constraint 4.12

SD = 4.58

3 Sub-contractor correlated challenges 3.94

SD = 5.72

4 Project interruption 3.94

SD = 6.39

5 Inappropriate authentication of contract documents 3.83

SD = 3.6

6 Competition offered by other  corporations 3.51

SD = 6.31

7 Inappropriate project scheduling and budgeting 3.25

SD = 2.92

8 materials price  increase 3.07

SD = 4.73

9 Loss resulted to variation of  rate of inflation 3.05

SD = 3.45

10 Communication problem between clients 3.03

SD = 4.47

11 Loss resulted to variation of interest rate 2.99

SD = 6.17

12 Increased cost of labour 2.95

SD = 6.88

13 Shortage of Materials  2.94

SD = 4.82

14 Internal problems of  management  2.93

SD = 4.19

15 Contract breached by project partner 2.91

SD = 1.99

16 Inappropriate feasibility study  of project  2.86

SD = 5.07

17 Unfamiliar conditions of site  2.83

SD = 2.32

18 Inappropriate organization structure  of a project  2.79

SD = 3.99

19 Loss resulted from fuel prices  rise  2.75

SD = 5.5

20 Design changes 2.74

SD = 3.76

21 Distance of site from urban area 2.6

SD = 6.27

22 Team work 2.56

SD = 3.52

23 Design drawings errors  2.53

SD = 4.78

24Project adverse   impact due to climatic condition 2.5

SD = 4.24

25 The project having no past similar experience 2.45

SD = 2.97

26 Procured materials having poor quality 2.39

SD = 3.48

27 material wasted by workers 2.3

SD = 4.19

28 Changes of Government policies increasing cost 2.24

SD = 3.37

29 Methodological risk 2.15

SD = 6.18

30 Lack negotiation clause in agreement 2.13

SD = 7.1

31 Poor disputes  and relations with partner 2.09

SD = 3.76

32 High point of difficulty in construction 2.07

SD = 5.04

33 Inflexible environmental regulations 1.93

SD = 3.67

34 Ineffectiveness of transportation amenities 1.84

SD = 2.98

35 Deficiency in supply of water 1.78

SD = 4.93

36 Failure in Equipment  1.77

SD = 3.12

37 Insufficient  project partner choice 1.73

SD = 2.23

38 Loss due to bureaucracy for late approvals 1.73

SD = 1.49

39 Disputes due to architect verses structural engineer 1.73  

SD = 4.84

40 Excess materials handling 1.71

SD = 3.78

41 Government standards and codes 1.7

SD = 4.95

42 Project partner bankruptcy  1.69

SD = 7.53

43 Site accidents 1.57

SD = 3.52

44 Accessory facilities price increase  1.54

SD = 3.65

45 Loss resulted from variation of exchange rate 1.43

SD = 3.34

46 Top management  changes1.43

SD = 2.54

47 Supply on fuel shortage 1.43

SD = 1.38

Conclusion  

The analysis conducted on McGrade house over has created and considered elective alternatives that enhance the first outline and development design. The last report fills in as the perfection of this analysis and a wellspring of thoughts for future undertakings. The discoveries and analysis are not planned at all to discover imperfections or saw botches in the genuine task. 

Building Information Modeling can be an extremely significant apparatus and process in building development. Through the Building Information Modeling Execution Planning Guide, created at Penn State, enables the greatest incentive to be accomplished with BIM. The McGrade house Project Team utilized BIM adequately on the task.

Esteem Engineering is the procedure that incorporates creating and assessing elective construction strategies and systems to increase the value of a venture. In Analysis two the recommendation of LEED components being prohibited from the esteem designing procedure investigates a potential circumstance if the green rooftop was incorporated into the esteem building process. Through expulsion of the green rooftop, expanding the R-Value of the rooftop gathering and extending the grey-water framework, esteem was hypothetically included through a cost reserve funds and lessening of Potable water use in the activity of the building. Also the green rooftop stack on the structure will be evacuated permitting the size and weight of the steel encircling individuals to be decreased.  

References

DelPico, W. (2012). Estimating Building Costs for the Residential and Light Commercial Construction Professional. New York: John Wiley & Sons.

Peterson, S. ( 2014). Estimating in Building Construction. Chicago: Pearson Education.

ASI Spray Insulation Professionals.(2011). Fireproofing + Thermal Insulation=Energy Savings and Protection: https://www.asispray.com.

Border, T. (2011). Transportation Cost Information. (N. Diehl, Interviewer) 

Clark, P. (2011). Metal Stud Crete-Earl Corporation. (N. Diehl, Interviewer) 

Computer Integrated Construction Research Program. (2010). Building Information Modeling Project Execution Planning Guide. 

District of Columbia Department of Energy. (2011). Green Roofs in the District – Showcase Projects: https://ddoe.dc.gov/ddoe. 

Gamino, T. (2011). Electrical Rough in Informtion. (N. Diehl, Interviewer) 

Greensulate. (2011). Green Roof Diagram and Research. What is a Green Roof?: https://www.greensulate.com.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.