IT Software Upgrade Project Proposal For ABC Pvt. Ltd.

Project Background and Description

ABC Pvt. Ltd. is a private single operator business that is willing to upgrade the existing IT setup to increase the overall efficiency of the operations and provide the employees with updated workstations to work on. The company operates with a small management team and around 50 employees who work on old and outdated desktop workstations. For some time, the employees have been reporting various issues like system lag, sudden stop of the system, long start up time, very slow calculations and others. Following these feedbacks, the company has decided to update the workstations as well as increase the number of workstations to increase the employee capacity of the company.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

As a part of the estimated plan, a total 500 workstations will be purchased and installed of which, 250 will be desktops and 250 will be laptops. In addition, while the existing systems run on Windows XP, Windows 2016 will be installed in the new systems.

The company currently runs with old and outdated workstations with Windows XP operating system and hence, the business processes are extremely slow. As a result, the customers are often dissatisfied with the services and choose to conduct business with other companies. Hence the company has decided to undertake a project in order to install new workstations in place of the old ones and also update the operating system to the most current version. Furthermore, the company is looking to expand and add more employees and hence, the total number of workstations will also have to be increased to accommodate more employees.

As per the initial estimation, a total of 500 new workstations required (including replacement and new systems). The company has decided that of these 500 workstations, 250 desktops will be purchased and the rest of the workstations will be laptops. While the laptops are much more expensive than desktops, they will save considerable amount of physical space. Furthermore, each of the management team members will be provided with laptop workstations only. Each new workstation will have fully updated and fully licensed Windows 2016 operating system installed. As per the estimation, the project will cost the company around $750,000.

The scope of the project includes the following.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
  • Selling the existing old workstations
  • Purchase of 250 desktop workstations with updated hardware configuration
  • Purchase of 250 laptop workstations with updated hardware configuration
  • Purchase of original licensed version of Windows 2016
  • Installation of all the workstations and respective software required in each of them

The main objective behind developing all these scope items is to upgrade the existing technical set up at the company as well as expand the business such that the company can recruit more employees and increase the business productivity. In order to achieve this ultimate objective of the project, it is required to deploy a technical team who will take care of installation of hardware and software. Furthermore, it is also required to conduct a training session for the employees who do not have sufficient technical expertise to work with the technically updated computers.

This particular project is specifically designed for supporting the expansion of the company for more business productivity. With the support of 500 employees, the company will have a huge opportunity to increase the overall business productivity as well as the annual revenue. With the increased capacity, the company will be able to conduct more projects that will enhance their services and allow them to enter new markets without any major constraints.

The project boundaries are defined using the following attributes.

Project Goals:

  • To increase the employee capacity to near 500
  • To upgrade existing technical set up

Project Assumptions:

  • It has been assumed that the expansion will be feasible with the opening of a new office building
  • It has been assumed that the updated technical setup will allow the desired functions of the company for the next five years
  • It has been assumed that the expansion will also help in increase in the business productivity of the company

Project Constraints:

  • The high budget is a major constraint of the project.
  • Without a new office building, the expansion process will not be possible due to lack of sufficient space.

The main requirements of the project are 500 computers and Windows 2016 operating system. Each of the computers must have at least the following configurations.

CPU

1.9GHz Intel Core i5-4300U (dual-core, 3MB cache, up to 2.9GHz with Turbo Boost)

Graphics

Intel HD Graphics 4400

RAM

4GB DDR3

Screen

14-inch, 2560 x 1440 IPS, IPS display with 10 point multi-touch control

Storage

180GB SSD

Ports

2 USB 3.0, mini DisplayPort, HDMI, Ethernet (via included dongle), headphone/mic combo jack

Connectivity

802.11ac Wi-Fi, Bluetooth 4.0

The main deliverables of the project are fully installed updated 500 workstations and Windows 2016 installed in each of them. All the deliverables are listed as follows.

Deliverable

Expected Delivery Date (MM/DD/YY)

Acceptance Criteria

Project Proposal

12/12/18

All details of the proposed system including the highlighted issues of the existing system are included in the proposal

Project Charter

12/25/18

All the details of the project including budget, schedule, communication plan and others are documented

List of Required Resources

12/25/18

All the required resources are listed in the document

Updated Technical Setup

6/14/19

All requirements of the project are met

Project Report Document

7/2/19

All details of the project including progress log are listed

The milestones are listed as follows.

Milestone

Target Date (MM/DD/YY)

Approval of the Proposal

Mon 12/17/18

Approval to Proceed with Project

Thu 1/3/19

Project Handover

Fri 6/14/19

Approval of the Project Report Document

Tue 7/2/19

Final Closing

Tue 7/2/19

#

Stakeholder Group

Primary Contact

Description

1

ABC Pvt. Ltd. Management Team

Mr. Aaron White, CEO

The management team will have better control over the operations with the upgraded IT setup. The management team members will have updated systems to work on with various features that will benefit their work.

2

ABC Pvt. Ltd. HRM Team

Mr. David Black, Chief HR Executive

With the expanded capacity, the HRM team will be able to recruit new employees for the company.

3

ABC Pvt. Ltd. Marketing and Operations Team

Mr. Sean Brown, Operations Manager

With the help of the upgraded IT system, the operations will be much more efficient and faster. In addition, there will be added functionalities like data analytics, cloud computing and others that will ultimately benefit the business related operations.

The risks in the project are identified as follows.

#

Identified Risk

P

I

Risk Priority

Strategy

1

The project is too costly and the company will not be able to provide the funds.

4

4

H

Avoid: The company should ensure the funds are available before start of project. If it cannot invest the entire system, loan can be taken from a sponsor.

2

The employees are not accustomed with the newly updated systems.

4

3

H

Accept: Training sessions can be conducted in which, the employees will be provided training regarding the use of the new systems.

3

Some of the workstations may not work properly or the software may not be licensed.

3

5

H

Transfer: The hardware company will be asked to replace the faulty systems as a part of the warranty scheme. In case of non-licensed software, legal help can be taken to take action against the software vendor.

The following are the exclusions from scope.

  • Recruitment of new employees as a part of the expansion plan of the company
  • Allocation of workstations to the employees
  • Training of the employees regarding use of the new systems

The project will be implemented in five main stages as per the standard project management methodology. These five stages are:

Project Discussion Phase – In this phase, there will be the identification of the issues of the current system and discussion between the board members regarding the issues. A proposal will also be submitted regarding the implementation of a possible solution.

Project Planning Phase – In this phase, the basic plan of the project will be developed including the project charter that includes project budget, schedule, risk matrix and others.

Project Initiation Phase – In this phase, the project will be initiated including procurement of funds purchase of necessary material resources and others.

Project Execution Phase – In this phase, the project will be executed and at the end of this phase, the final outcome of the project has to be delivered.

Project Closing Phase – In this phase, the project will be reviewed, documented and closed after all payments and residual works are completed.

In order to determine the budget of the project, the unit costs of the resources usages are determined in the following table.

Resource Name

Type

Initials

Max. Units

Std. Rate

Project Manager

Work

P

100%

$120.00/hr

Manager of IT Department

Work

M

100%

$105.00/hr

Project Team Leader

Work

P

100%

$102.00/hr

Technical Team

Work

T

100%

$600.00/hr

Computer (1 Unit)

Material

C

$250.00

Laptop (1 unit)

Material

L

$300.00

Microsoft 2016 License

Material

M

$6,000.00

Based on these costs and allocation of the costs to the project schedule, the total budget can be developed as shown in the following table.

Task Name

Duration

Start

Finish

Resource Names

Cost

Information Technology Software Upgrade Project

157 days

Mon 11/26/18

Tue 7/2/19

$722,644.00

   Project Discussion Phase

16 days

Mon 11/26/18

Mon 12/17/18

$15,960.00

      Survey the Requirements of the Existing System

5 days

Mon 11/26/18

Fri 11/30/18

Manager of IT Department

$4,200.00

      Call Management Team Meeting

1 day

Mon 12/3/18

Mon 12/3/18

Manager of IT Department

$840.00

      Undertake the Meeting

2 days

Tue 12/4/18

Wed 12/5/18

$3,600.00

         Discuss the Current Issues

0.5 days

Tue 12/4/18

Tue 12/4/18

Manager of IT Department, Project Manager

$900.00

         Discuss Possible Issues

0.5 days

Tue 12/4/18

Tue 12/4/18

Manager of IT Department, Project Manager

$900.00

         Discuss Possible New Solutions

0.5 days

Wed 12/5/18

Wed 12/5/18

Manager of IT Department, Project Manager

$900.00

         Agree Upon Software Upgrade Process

0.5 days

Wed 12/5/18

Wed 12/5/18

Manager of IT Department, Project Manager

$900.00

      Submit Project Proposal

5 days

Thu 12/6/18

Wed 12/12/18

Project Manager

$4,800.00

      Analysis of Proposal

3 days

Thu 12/13/18

Mon 12/17/18

Manager of IT Department

$2,520.00

      Approval of the Proposal

0 days

Mon 12/17/18

Mon 12/17/18

Manager of IT Department

$0.00

   Project Planning Phase

13 days

Tue 12/18/18

Thu 1/3/19

$11,520.00

      Assign Project to Project Manager

2 days

Tue 12/18/18

Wed 12/19/18

Manager of IT Department

$1,680.00

      Develop Project Carter

4 days

Thu 12/20/18

Tue 12/25/18

$3,264.00

         Determine the Scope of the Project

1 day

Thu 12/20/18

Thu 12/20/18

Project Team Leader

$816.00

         Determine Appropriate Project Schedule

0.5 days

Fri 12/21/18

Fri 12/21/18

Project Team Leader

$408.00

         Estimate Accurate Budget for Project

1.5 days

Fri 12/21/18

Mon 12/24/18

Project Team Leader

$1,224.00

         Prepare List of Resources

1 day

Tue 12/25/18

Tue 12/25/18

Project Team Leader

$816.00

      Identify Possible Risks of the Project

3 days

Wed 12/26/18

Fri 12/28/18

Project Manager

$2,880.00

      Prepare Management Plan for the Risks

3 days

Mon 12/31/18

Wed 1/2/19

Project Manager

$2,880.00

      Submit the Project Charter

1 day

Thu 1/3/19

Thu 1/3/19

Project Team Leader

$816.00

      Approval to Proceed with Project

0 days

Thu 1/3/19

Thu 1/3/19

Project Manager

$0.00

   Project Initiation Phase

24 days

Fri 1/4/19

Wed 2/6/19

$242,764.00

      Hire Technical Team

4 days

Fri 1/4/19

Wed 1/9/19

Project Team Leader

$3,264.00

      Purchase Computers

15 days

Thu 1/10/19

Wed 1/30/19

Computer (1 Unit)[250], Laptop (1 unit)[250], Technical Team

$209,500.00

      Purchase Authentic Versions of Windows 2016

5 days

Thu 1/31/19

Wed 2/6/19

Microsoft 2016 License[1], Technical Team

$30,000.00

   Project Execution Phase

92 days

Thu 2/7/19

Fri 6/14/19

$441,600.00

      Install the Computers in the Office

60 days

Thu 2/7/19

Wed 5/1/19

Technical Team

$288,000.00

      Install Windows 2016 in Each System

10 days

Thu 5/2/19

Wed 5/15/19

Technical Team

$48,000.00

      Install Business Software in Each System

10 days

Thu 5/16/19

Wed 5/29/19

Technical Team

$48,000.00

      Connect System to Central Server

2 days

Thu 5/30/19

Fri 5/31/19

Technical Team

$9,600.00

      Test the Systems

10 days

Mon 6/3/19

Fri 6/14/19

Technical Team

$48,000.00

      Project Handover

0 days

Fri 6/14/19

Fri 6/14/19

Technical Team

$0.00

   Project Closing Phase

12 days

Mon 6/17/19

Tue 7/2/19

$10,800.00

      Review the Project

5 days

Mon 6/17/19

Fri 6/21/19

Project Manager

$4,800.00

      Finalize All Remaining Payments

2 days

Mon 6/24/19

Tue 6/25/19

Project Manager

$1,920.00

      Prepare Project Report Document

5 days

Wed 6/26/19

Tue 7/2/19

Project Team Leader

$4,080.00

      Approval of the Document

0 days

Tue 7/2/19

Tue 7/2/19

Manager of IT Department

$0.00

      Final Closing

0 days

Tue 7/2/19

Tue 7/2/19

Manager of IT Department

$0.00

Hence, the total approximate budget for the project is $750,000.

The timeline of the project is also shown in the form a Gantt chart as follows.

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Burke, R., & Barron, S. (2014). Project management leadership: building creative teams. John Wiley & Sons.

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.

Crawford, J. K. (2014). Project management maturity model. Auerbach Publications.

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Kilibarda, G. D., Šobaji?, V. M., Beri?, I. M., & Jovanovi?, P. M. (2016). Software project management. Tehnika, 71(1), 145-152.

Kundra, T., & Sharma, A. (2015). Software project management. Int. J. Res.

Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.