Implementation Of SAP S/4HANA For SAP Business All-in-one – Project Charter

Purpose of the project charter

Project name: Implementation of SAP S/4HANA for SAP Business All-in-one

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The main aim of the charter is to provide the preliminary delineation of the roles and the responsibilities of the project team along with the objectives of the project. The charter aims in evaluating the objectives of the project, project requirements and deliverables of the project. The charter will provide an idea of the schedule and the major project deliverables along with an approach to system development. Thus this project charter will act as a key reference to the project manager and the project team while implementing the project.

With an aim of eliminating the operational weakness of Yes Chemist, which is a group of independent Pharmacies operating in major cities of Australia, a project has been proposed to implement SAP S/4 HANA. In order to implement the project a contract has been given to Victoria University Information Systems Consulting (VUISC).

The objective of the project is to replace the existing legacy accounting system to implement the SAP S/4 HANA. The scope of the SAP implementation project involves installation and delivery of a proper hardware, software and complete configuring of the SAP system including the testing, and provisioning the end user training. The contract for the entire work has been provided to VUISC.  The project further involves migration of data nfrom the existing system to SAP All-in –one module that is to be implemented.

The project is essential as with the increase in the size of the business it was becoming difficult for the organisation to maintain and manage their complex business processes. With the implementation of SAP S/4HANA, all the business operations can be streamlined and can be easily maintained. The entire project is divided into a number of phases such as requirement phase, integration, acceptance and sign off phase, testing phase, data conversion phase, Documentation and training. The expected start date of the project is 25th July 2017.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The functional requirements of the project are to be identified in order to design the new system. In order to successfully implement a project, it is essential to refurbish the components of the operational head office. The requirement of the project further incorporates purchase of hardware, conversion of the existing data to migrate to the new system and testing the new system. After the implementation of the new system, it is the responsibility of the contractor to provide training to the staffs.

The major deliverables of the project along with the key milestone of the project are as follows-

Analysis of the System Requirements

Conversion of Data

Implementation of SAP S/4HANA

Milestone: Completion of Server and System Installation

Integration and Testing of new SAP system

Documenting the entire Project

Training the staffs and employees

Acceptance Testing and Project Sign Off

Milestone: Completion of Training and Project Sign Off

The project is a complex project and therefore the entire project is divided into a number of controllable phases. Each phase has a number of tasks, successful completion of which will ensure the successful delivery of the project. The details about the major project phases, milestone and tasks are represented in the following table.
 

Table 1 Brief project schedule

Entry type

Description

Phase

Requirement Phase

Task

Obtaining the functional requirements

Task

Aligning the functional requirements with Users’ expectations

Task

Preparation of Project Charter

Phase

Data Conversion

Task

Understanding the legacy data structure

Task

Setting up an automated data extractor

Task

Data validation and cleansing

Task

Developing the automated script

Task

Testing and defect rectification

Task

Analysis of migrated data and manual rectification

Milestone

Completion of server Installation

Phase

Integration and Testing

Task

New system to be integrated with e gate feature

Task

End to end testing

Task

System Integration Testing

Milestone

Completion of System Installation

Phase

Documentation and Training

Task

Development of application functionality manuals

Task

Reviewing the standard of SAP business All-in-one

Task

Customization of the training programs

Task

Imparting the Training

Phase

Acceptance Testing and Sign Off

Task

Completion of hardware and Software application

Task

Completion of Training

Task

Completion of User acceptance testing

Milestone

Completion of Training and Sign Off

This section of the project charter will provide the details of the major project cost that the project manager needs to consider.

SAP Licensing Fee for 300 users

$150,000

Virtual servers cost

$3,000

Cost of demolishing

$15,000

Project Manager (Cost/hour)

$195

Business Analyst (Cost/hour)

$130

Technical Writer (Cost/hour)

$95

Trainer (Cost/hour)

$115

Systems Integrator (Cost/hour)

$105

Application programmer (Cost/hour)

$95

Technical Officer (Cost/hour)

$85

Data Entry Officer (Cost/hour)

$60

Administrative officer (Cost/hour)

$50

The key project quality management issues associated with the project are as follows-

  1. The project will not be accepted unless the data conversion phase is performed accurately
  2. The project will not be accepted unless the training is completed
  3. The project will not be accepted unless the software and hardware installation is complete
  4. The project will not be accepted unless the user acceptance test is completed.

The duration of the project is represented as follows-

Task Name

Duration

Start

Finish

SAP Implementation

254 days

Tue 25-07-17

Fri 13-07-18

   Requirement Phase

32 days

Tue 25-07-17

Wed 06-09-17

      Obtaining the functional requirements

10 days

Tue 25-07-17

Mon 07-08-17

      Aligning the functional requirements with Users’ expectations

15 days

Tue 08-08-17

Mon 28-08-17

      Preparation of Project Charter

7 days

Tue 29-08-17

Wed 06-09-17

   Data Conversion

22 days

Thu 07-09-17

Fri 06-10-17

      Understanding the legacy data structure

3 days

Thu 07-09-17

Mon 11-09-17

      Setting up an automated data extractor

2 days

Tue 12-09-17

Wed 13-09-17

      Data validation and cleansing

3 days

Thu 14-09-17

Mon 18-09-17

      Developing the automated script

2 days

Tue 19-09-17

Wed 20-09-17

      Testing and defect rectification

5 days

Thu 21-09-17

Wed 27-09-17

      Analysis of migrated data and manual rectification

7 days

Thu 28-09-17

Fri 06-10-17

   Completion of server Installation

0 days

Fri 06-10-17

Fri 06-10-17

   Integration and Testing

90 days

Mon 09-10-17

Fri 09-02-18

      New system to be integrated with e gate feature

30 days

Mon 09-10-17

Fri 17-11-17

      End to end testing

15 days

Mon 20-11-17

Fri 08-12-17

      System Integration Testing

45 days

Mon 11-12-17

Fri 09-02-18

   Completion of System Installation

0 days

Fri 09-02-18

Fri 09-02-18

   Documentation and Training

75 days

Mon 12-02-18

Fri 25-05-18

      Development of application functionality manuals

30 days

Mon 12-02-18

Fri 23-03-18

      Reviewing the standard of SAP business All-in-one

10 days

Mon 26-03-18

Fri 06-04-18

      Customization of the training programs

15 days

Mon 09-04-18

Fri 27-04-18

      Imparting the Training

20 days

Mon 30-04-18

Fri 25-05-18

   Acceptance Testing and Sign Off

35 days

Mon 28-05-18

Fri 13-07-18

      Completion of hardware and Software application

10 days

Mon 28-05-18

Fri 08-06-18

      Completion of Training

15 days

Mon 11-06-18

Fri 29-06-18

      Completion of User acceptance testing

10 days

Mon 02-07-18

Fri 13-07-18

   Completion of Training and Sign Off

0 days

Fri 13-07-18

Fri 13-07-18

Mr Russell will authorize the project charter. 

Operational Manager (VUISC) Shah Miah

Burke, R. and Barron, S., 2014. Project management leadership: building creative teams. John Wiley & Sons.

Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.

Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.

Heagney, J., 2016. Fundamentals of project management. Amacom.

Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.

Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.