Development Of Cloud-Based ERP System For Blach Construction Company
System Vision and Problem Description
The paper mainly reflects on the development of cloud ERP system within the organization “Blach construction company” which is one of the construction company of Australia that has its offices in Silicon Valley and Central coast. It is identified that the organization uses ERP system in order to manage its operations. However, the use of ERP system creates number of challenges as well as issues including expensive installation, resistance in sharing data, difficulty in using the system as well as problem is accessing information outside the office. In order to resolve the problem, the organization wants to move its ERP system within cloud so that the operations of the organization can be managed quite effectively.
1.2 System capabilities
The system capabilities of the cloud-based ERP system mainly include:
- Customization of work
- Migrating the data and information into cloud
- Transferring knowledge as well as technology
- Checking the infrastructure of cloud
1.3 Expected business benefits
The benefits that are expected from the development of cloud-based ERP system are elaborated below:
Access from anywhere: It is found that important information and data of the organization can be accessed from anywhere, anytime by the staffs as well as customers of the organization.
No staff time: No staff time is mainly needed for maintaining or upgrading the hardware the organization grows.
Current functionality: Current functionality is always present as the cloud vendor maintains as well as updates the software.
Backup: Data can be quite easily backed up with the help of proper disaster recovery plan of the organization.
2. Quantify project approval factors
2.1 Time that is estimated for completion of project
The time that is generally required for the cloud ERP system development is generally given in the below table.
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Development of cloud-based ERP system in Blach construction company, Australia |
85 days |
Thu 22-11-18 |
Wed 20-03-19 |
1 |
Initiation phase |
15 days |
Thu 22-11-18 |
Wed 12-12-18 |
1.1 |
Development of project business plan |
3 days |
Thu 22-11-18 |
Mon 26-11-18 |
1.2 |
Cost benefit analysis |
3 days |
Tue 27-11-18 |
Thu 29-11-18 |
1.3 |
Establishing the charter for the project |
4 days |
Fri 30-11-18 |
Wed 05-12-18 |
1.4 |
Recruiting the staffs |
5 days |
Thu 06-12-18 |
Wed 12-12-18 |
1.5 |
Milestone 1: Completion of initiation phase |
0 days |
Wed 12-12-18 |
Wed 12-12-18 |
2 |
Planning phase |
24 days |
Thu 06-12-18 |
Tue 08-01-19 |
2.1 |
Developing the plan for the project |
3 days |
Thu 06-12-18 |
Mon 10-12-18 |
2.2 |
Developing plan for project resources |
2 days |
Tue 11-12-18 |
Wed 12-12-18 |
2.3 |
Development of financial plan |
4 days |
Thu 13-12-18 |
Tue 18-12-18 |
2.4 |
Developing project quality plan |
3 days |
Wed 19-12-18 |
Fri 21-12-18 |
2.5 |
Planning for risk management |
2 days |
Mon 24-12-18 |
Tue 25-12-18 |
2.6 |
Project acceptance planning |
3 days |
Wed 26-12-18 |
Fri 28-12-18 |
2.7 |
Project communication plan |
4 days |
Mon 31-12-18 |
Thu 03-01-19 |
2.8 |
Developing plan for project procurement |
3 days |
Fri 04-01-19 |
Tue 08-01-19 |
2.9 |
Milestone 2: Completion of planning phase |
0 days |
Tue 08-01-19 |
Tue 08-01-19 |
3 |
Execution phase |
41 days |
Wed 09-01-19 |
Wed 06-03-19 |
3.1 |
Identifying the requirements for the business |
5 days |
Wed 09-01-19 |
Tue 15-01-19 |
3.2 |
Cloud based ERP system |
4 days |
Wed 16-01-19 |
Mon 21-01-19 |
3.3 |
Customization of work |
4 days |
Tue 22-01-19 |
Fri 25-01-19 |
3.4 |
Data migration |
5 days |
Mon 28-01-19 |
Fri 01-02-19 |
3.5 |
Checking of infrastructure |
4 days |
Mon 04-02-19 |
Thu 07-02-19 |
3.6 |
Customization |
3 days |
Fri 08-02-19 |
Tue 12-02-19 |
3.7 |
Managing change |
4 days |
Wed 13-02-19 |
Mon 18-02-19 |
3.8 |
Transfer of knowledge and technology |
4 days |
Tue 19-02-19 |
Fri 22-02-19 |
3.9 |
Testing of project management |
3 days |
Mon 25-02-19 |
Wed 27-02-19 |
3.10 |
Testing system integration |
2 days |
Thu 28-02-19 |
Fri 01-03-19 |
3.11 |
Testing user-acceptance |
3 days |
Mon 04-03-19 |
Wed 06-03-19 |
3.12 |
Milestone 3: Completion of execution phase |
0 days |
Wed 06-03-19 |
Wed 06-03-19 |
4 |
Closing phase |
10 days |
Thu 07-03-19 |
Wed 20-03-19 |
4.1 |
Reviewing the project |
4 days |
Thu 07-03-19 |
Tue 12-03-19 |
4.2 |
Sign off the project stakeholders |
4 days |
Wed 13-03-19 |
Mon 18-03-19 |
4.3 |
Post go-live support |
2 days |
Tue 19-03-19 |
Wed 20-03-19 |
4.4 |
Milestone 4: Completion of closure phase |
0 days |
Wed 20-03-19 |
Wed 20-03-19 |
2.2 Development cost of the project
The budget that is generally needed in order to develop the cloud-based ERP system are provided below.
WBS |
Task Name |
Duration |
Resource Names |
Cost |
0 |
Development of cloud-based ERP system in Blach construction company, Australia |
85 days |
AUD49,440.00 |
|
1 |
Initiation phase |
15 days |
AUD3,800.00 |
|
1.1 |
Development of project business plan |
3 days |
Project planner, Project manager |
AUD1,320.00 |
1.2 |
Cost benefit analysis |
3 days |
Financial manager |
AUD480.00 |
1.3 |
Establishing the charter for the project |
4 days |
Project planner |
AUD800.00 |
1.4 |
Recruiting the staffs |
5 days |
Project manager |
AUD1,200.00 |
1.5 |
Milestone 1: Completion of initiation phase |
0 days |
AUD0.00 |
|
2 |
Planning phase |
24 days |
AUD9,960.00 |
|
2.1 |
Developing the plan for the project |
3 days |
Project planner, Supervisor |
AUD1,128.00 |
2.2 |
Developing plan for project resources |
2 days |
Project planner, Financial manager, Human resource manager |
AUD1,040.00 |
2.3 |
Development of financial plan |
4 days |
Project planner, Financial manager |
AUD1,440.00 |
2.4 |
Developing project quality plan |
3 days |
Supervisor, Financial manager, Risk analyst |
AUD1,488.00 |
2.5 |
Planning for risk management |
2 days |
Risk analyst, Tester |
AUD624.00 |
2.6 |
Project acceptance planning |
3 days |
Project planner, Supervisor |
AUD1,128.00 |
2.7 |
Project communication plan |
4 days |
Project planner, Supervisor |
AUD1,504.00 |
2.8 |
Developing plan for project procurement |
3 days |
Project planner, Supervisor, Financial manager |
AUD1,608.00 |
2.9 |
Milestone 2: Completion of planning phase |
0 days |
AUD0.00 |
|
3 |
Execution phase |
41 days |
AUD33,520.00 |
|
3.1 |
Identifying the requirements for the business |
5 days |
Supervisor, Database manager, Human resource manager |
AUD2,480.00 |
3.2 |
Cloud based ERP system |
4 days |
Supervisor, Technical engineer |
AUD1,344.00 |
3.3 |
Customization of work |
4 days |
Risk analyst, Technical engineer, Project planner, Additional cost[1] |
AUD14,080.00 |
3.4 |
Data migration |
5 days |
Database manager, Technical engineer, Tester |
AUD2,360.00 |
3.5 |
Checking of infrastructure |
4 days |
Supervisor, Risk analyst, Technical engineer, Tester |
AUD2,592.00 |
3.6 |
Customization |
3 days |
Database manager, Project manager, Technical engineer |
AUD1,680.00 |
3.7 |
Managing change |
4 days |
Project planner, Supervisor, Database manager, Risk analyst, Technical engineer |
AUD3,424.00 |
3.8 |
Transfer of knowledge and technology |
4 days |
Supervisor, Database manager, Risk analyst, Technical engineer |
AUD2,624.00 |
3.9 |
Testing of project management |
3 days |
Risk analyst, Tester |
AUD936.00 |
3.10 |
Testing system integration |
2 days |
Supervisor, Database manager, Technical engineer |
AUD992.00 |
3.11 |
Testing user-acceptance |
3 days |
Supervisor, Technical engineer |
AUD1,008.00 |
3.12 |
Milestone 3: Completion of execution phase |
0 days |
AUD0.00 |
|
4 |
Closing phase |
10 days |
AUD2,160.00 |
|
4.1 |
Reviewing the project |
4 days |
Project planner |
AUD800.00 |
4.2 |
Sign off the project stakeholders |
4 days |
Project manager |
AUD960.00 |
4.3 |
Post go-live support |
2 days |
Project planner |
AUD400.00 |
4.4 |
Milestone 4: Completion of closure phase |
0 days |
AUD0.00 |
2.3 Estimated annual operating costs
The operating cost that is generally needed by the cloud-based ERP system are provided below.
Recurring expenses |
Amount |
Hosting in the server |
$6,000 |
Internet connection |
$3,000 |
Training |
$3,000 |
Renewal (Equipment) |
$3,000 |
Total Costs |
$15,000 |
2.4 Cost benefit analysis
2.4.1 Anticipated benefits
The benefits that are achieved from the cloud-based ERP system deployment are given below. It is found that the anticipated benefits generally include both tangible as well as intangible benefits.
Tangible benefits: The tangible benefits that are achieved from the cloud-based ERP system development are listed below.
- Provide access of information from anywhere irrespective of the location
- Reduces staff employment
- Reduces extra expenses on various technological needs
Intangible benefits: The intangible benefits which are generally achieved from the cloud-based ERP system development are provided below:
- Enhancing satisfaction level among the staffs as they can get access of information even from their home
- Keep the inconsistencies as well as glitches away
- 2.4.2 Table for estimated annual benefits
The benefits that are generally achieved annually due to the cloud-based ERP development is showcased in the below table.
Benefit |
Amount |
Faster implementation |
$5,000 |
Fast performance |
$7,000 |
Minimizing technological expenses |
$6,000 |
Reduction in the number of staffs |
$6,00 |
Total amount |
$24,000 |
3. Perform a risk and feasibility analysis
3.1 Determining feasibility and organizational risks
The organizational feasibility and risks which are mainly related with the project are generally elaborated below:
Data security: This is considered as one of the biggest issues that is related with the cloud ERP. It is found that when the information is made web accessible then the problem of data breaches become of the legitimate concern. Thus, the organization faces number of security related issues.
Cost consideration: It is found that though the overall solution of cloud is considered to be very much cost effective but the organization faces financial issue when long term cost for licencing of cloud ERP system is required. When the organization wants to move to cloud the organization initially needs to spend certain amount of money for getting the license.
System Capabilities
Inability to adapt: In spite of the intention of moving to the cloud, unfamiliarity as well as inability to adopt the new information system by the organizational staff is seen due to lack of preparation. Thus, the staffs who generally have very much limited information as well as knowledge related with technology generally creates difficulties for adopting the system.
3.2 Evaluating technological risks as well as feasibility
The employees who are mainly associated with the organization are provided with proper training facility of 2 days if it is quite difficult for the employees of the organization to manage the operations in cloud. Additionally, both video as well as presentation resources are generally shared among the staffs so that the employees can get proper idea about how the organizational operations will be managed for stored. Moreover, the resources also help in providing proper idea about the process of data recovery in case of any problem.
It is found that for checking the feasibility of the cloud-based ERP system, it is very much necessary to test the ERP system for making sure that the entire operations as well as functions of the organizations can be effectively managed.
3.3 Asses resource risks and feasibility
It is analyzed that it is quite necessary for the organizational staffs to properly understand the roles as well as responsibilities which are mainly needed for executing each of the project tasks in order to develop the cloud ERP system. If the employees are unable to analyze the needs as well as requirements for cloud ERP system development there is number of probabilities of risk occurrences.
3.4 Identify schedule feasibility and project risks
If the schedule of the project is not properly managed then it is analyzed that there is a high chance that the project will not get completed within the time that is expected and thus in order to finish the project, it is quite necessary to extend the completion date of the project. Extension in the project time generally enhances the cost that is associated with the project which further creates financial issues. For resolving the issues, it is quite important to schedule the project activities so that the cloud ERP can be developed within the expected budget and time.
4. Project environment establishment
4.1 Information outlined in the table.
Information capture
Information capture |
Electronic tools |
User accessibility |
Project schedule |
MS-Project |
Project manager |
Annual cost associated with project operation |
MS-Project |
Project manager |
Annual benefits from the project |
MS-Project |
Project Manager |
Project status |
MS-Project |
All user |
User documentation |
MS-Word |
All User |
Design specification |
Microsoft Visio |
Project manager |
4.2 Describe the work environment
The work environment is quite important for completing the project successfully. The tables that are provided below reflects on the various types of resources which are generally needed for the work environment of the project
Hardware and software
Item |
Description |
Resource |
Server |
Dell PowerEdge T440 Tower Server |
Blach construction company (Expense) |
Computers |
Dell inspiron 3477 and Dell inspiron 5000 |
Blach construction company (Expense) |
MS-Project |
Microsoft Project 360 |
License-Owned by author |
MS-Word |
Microsoft Word 360 |
License-Owned by author |
MS-Visio |
Microsoft Visio 360 |
License-Owned by author |
Support Staff
Item |
Description |
Resource |
Admin Staff |
Organizational staff |
Blach construction company |
4.3 Description of the procedures and processes that will be utilized
The procedures as well as processes which are generally needed in the project are generally elaborated below:
Testing: Testing the performance will be done for making sure that the cloud ERP system will be capable of managing the organizational operations and functions of the organization quite effectively. If any case of technical failure is seen, then it is necessary to make improvements.
Expected Business Benefits
Documentation: All the information as well as details that are mainly associated with the meetings, feedback as well as design specification are generally documented for keeping record so that the information can be used in the future when needed.
Deliverables: After completion of the project, the Blach construction company can be able to store the organizational data within cloud and thus if the staffs of the organization want to access information can easily access data irrespective of time and location. This assists in increasing flexibility of the staffs. Moreover, the data and information of the customers are stored properly on the cloud and additionally the information recovery facility is also provided with the help of cloud ERP.
5. Schedule the work
5.1 Work breakdown structure
The structure of work breakdown is given below:
WBS |
Task Name |
0 |
Development of cloud-based ERP system in Blach construction company, Australia |
1 |
Initiation phase |
1.1 |
Development of project business plan |
1.2 |
Cost benefit analysis |
1.3 |
Establishing the charter for the project |
1.4 |
Recruiting the staffs |
1.5 |
Milestone 1: Completion of initiation phase |
2 |
Planning phase |
2.1 |
Developing the plan for the project |
2.2 |
Developing plan for project resources |
2.3 |
Development of financial plan |
2.4 |
Developing project quality plan |
2.5 |
Planning for risk management |
2.6 |
Project acceptance planning |
2.7 |
Project communication plan |
2.8 |
Developing plan for project procurement |
2.9 |
Milestone 2: Completion of planning phase |
3 |
Execution phase |
3.1 |
Identifying the requirements for the business |
3.2 |
Cloud based ERP system |
3.3 |
Customization of work |
3.4 |
Data migration |
3.5 |
Checking of infrastructure |
3.6 |
Customization |
3.7 |
Managing change |
3.8 |
Transfer of knowledge and technology |
3.9 |
Testing of project management |
3.10 |
Testing system integration |
3.11 |
Testing user-acceptance |
3.12 |
Milestone 3: Completion of execution phase |
4 |
Closing phase |
4.1 |
Reviewing the project |
4.2 |
Sign off the project stakeholders |
4.3 |
Post go-live support |
4.4 |
Milestone 4: Completion of closure phase |
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), 761-778.
Braglia, M., & Frosolini, M. (2014). An integrated approach to implement project management information systems within the extended enterprise. International Journal of Project Management, 32(1), 18-29.
Buede, D. M., & Miller, W. D. (2016). The engineering design of systems: models and methods. John Wiley & Sons.
Chen, Y. C., Chung, T. Y., Lin, C. S., Wu, T. S., & Leu, H. S. (2015). Investigation report on an event of neurosurgical postoperative surgical site infections. Journal of Microbiology, Immunology and Infection, 48(2), S115.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.
Hosseini, M., Shahri, A., Phalp, K. & Ali, R., (2016). June. A modelling language for transparency requirements in business information systems. In International Conference on Advanced Information Systems Engineering (pp. 239-254). Springer, Cham.
Ismail, N. A., & King, M. (2014). Factors influencing the alignment of accounting information systems in small and medium sized Malaysian manufacturing firms. Journal of Information Systems and Small Business, 1(1-2), 1-20.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project risk management methodology for small firms. International journal of project management, 32(2), 327-340.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Preston, R. P., & Roy, J. (2017). Use of unmanned aerial vehicles to supplement conventional investigation methods for underground open void stability and mitigation.
Razak, S. A., Othman, S. H., Aldolah, A. A., & Ngadi, M. A. (2016). Conceptual investigation process model for managing database forensic investigation knowledge. Res. J. Appl. Sci., Eng. Technol., 12(4), 386-394.
Sánchez, M. A. (2015). Integrating sustainability issues into project management. Journal of Cleaner Production, 96, 319-330.
Serrador, P., & Pinto, J. K. (2015). Does Agile work?—A quantitative analysis of agile project success. International Journal of Project Management, 33(5), 1040-1051.
Snyder, C. S. (2014). A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.
Volk, R., Stengel, J., & Schultmann, F. (2014). Building Information Modeling (BIM) for existing buildings—Literature review and future needs. Automation in construction, 38, 109-127.
Wolken-Möhlmann, G., Bendlin, D., Buschmann, J., & Wiggert, M. (2016). Project schedule assessment with a focus on different input weather data sources. Energy Procedia, 94, 517-522.