Annual Fund Raising Charity Event

Objectives and Scope of the Project

This project is based on an annual fund raising charity event to be held at the end of the academic year at London School of Business and Management. The organization has provided a green light to proceed with the project and standard project management process will need to be followed in order to execute the event successfully. For this purpose, a project management team consisting of a number of stakeholders and project team members will be recruited who will manage all the activities of the project including preparation and the execution of the entire event successfully. However, a deadline has been set for the event and a minimum revenue cap has been decided and hence, the event must be executed in order to fulfill both the requirements. The main objective of this event is to raise significant amount of funds that will entirely donated to charity.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

In this report, a detailed project plan has been provided for the development and preparation of the proposed event of May 2018.

As per the proposed plan for the project, the fund raising event will be held after the academic year comes to an end in May 2018. In this fund raising event, a number of stage performances and other popular events will be held. The revenue that will be generated from the event will be donated to charity. According to initial estimations, the minimum expected revenue is £2018.

As a part of the plan, the event will mark the end of the academic year and hence, special performance awards will be given to the best achievers and performers in the academic year. In addition, the fund raising event will also incorporate music and drama performances from the college students as well as participation of some popular singers / performers. The income from tickets and revenues generated will be donated to some charities including orphanages, old age homes and others.

The scope of the project includes the following.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
  • Preparation for the fundraising event is within the scope of the project.
  • Promotion of the event for maximum participation is within the scope of the project.

The main objectives of the project are as follows.

  • To develop a suitable implementation plan for the project
  • To estimate accurate budget and time for project
  • To prepare a list of activities to be undertaken during the event
  • To procure a suitable sponsor for the project
  • To host the event on the selected date

The assumptions of the project are as follows.

  • It has been assumed that the project will be financially feasible for the organization.
  • It has been assumed that the participation in the event will be sufficiently high so that the revenue cap can be executed.
  • It has been assumed that the students of the college will actively participate in the event for raising the funds.

The constraints of the project are as follows.

  • Lack of sufficient time for preparation may be a constraint.
  • Unclear definition of the event details to be undertaken can be a constraint.
  • Lack of sufficient participation of performers and the viewers can be a significant constraint.
  • Insufficient funds for the project may be a source of constraint for the project.

The goals of the project include the following:

  • Execution of the Fundraising Event
  • Execution of End Year Performance Awards
  • Revenue of At Least £2018
  • Host Stage Performances (Music, Drama, etc.)

The stakeholders for the project have been analyzed as follows.

Stakeholder

Name

Responsibilities

Project Manager

Harrison James

Management of entire event, monitoring of the preparation and execution, change management, controlling other stakeholders and project activities, etc.

Finance Manager

Steve Selvig

Management of event funds, allocation of resources to the project team,

Event Manager

Edward Stevenson

Management and planning of the entire event, execution of all the performances and activities at the event

Site Manager

Joseph King

Management of the preparation for event, decoration of the auditorium, preparation of performance stage and audience zone, etc.

Rewards Manager

Marcus Taylor

Presentation of rewards to the best performing students, management of the academic event, etc.

The project manager has a number of duties that include management of the entire project. Hence, the project manager will take part in the planning of the project along with the recruitment of other stakeholders of the project. Furthermore, the project manager will need to monitor the progress of the project and make suitable changes if necessary. No activity in the project should be executed without the prior approval of the project manager.

Assumptions and Constraints

Project Signoff – Another important duty of the project manager is to complete the project signoff after the project evaluation is over. After the execution phase is over, each of the stakeholders will review the project and then forward it to the project manager along with the project report document. The project manager will review the entire project and if satisfied, he will complete the signoff and officially close the project.

The estimated costs include the following (involving both material and human resources).

Units/Hrs

Cost/Unit/Hr

Subtotals

WBS Level 1 Totals

% of Totals

Resource/WBS Items

1. Project Management

 

 

 

£                        1,570

29%

Project Manager

45

£ 10

£           450

Project Team Members

100

£ 6

£           600

Event Management Team

65

£ 8

£           520

2. Promotions

 

 

 

£                            625

12%

Advertisements

25

£ 10.00

£           250

Leaflets

250

£ 0.50

£           125

Passes and Invitations

25

£ 10.00

£           250

3. Decoration of Hall

 

 

 

£                            750

14%

Internal Decorations

150

£ 2.00

£           300

External Decorations

150

£ 3.00

£           450

4. Food for Audience

 

 

 

£                            600

11%

Burgers

300

£ 1.00

£           300

French Fry Packets

300

£ 0.50

£           150

Soft Drinks

300

£ 0.50

£           150

5. Payments to Performers

 

 

 

£                            875

16%

Music Performers

5

£ 100.00

£           500

Drama Performers

5

£ 75.00

£           375

6. Reserves (20% of Total Estimate)

 

 

 

£                  1,000.00

TOTAL

 

 

 

£                  5,420.00

The projected revenue from the project will include the following.

Source

Revenue

Ticket Sales

£5000

Board Investment

£10000

Income from Promotions and Donations

£5000

TOTAL

£20,000

Hence, the estimated profit from the project is £ (20000 – 16500) = £3500.

The estimated time for the project is shown in the following table.

Task Name

Duration

Start

Finish

Predecessors

Fund Raising Event

75 days

Mon 05-02-18

Fri 18-05-18

   Phase 1: Planning

13 days

Mon 05-02-18

Wed 21-02-18

      Initial Planning for the Event

2 days

Mon 05-02-18

Tue 06-02-18

      Discussions between University Board Members

2 days

Wed 07-02-18

Thu 08-02-18

2

      Determination of Event Objectives

1 day

Fri 09-02-18

Fri 09-02-18

3

      Initial Planning for Budget

1 day

Mon 12-02-18

Mon 12-02-18

4

      Meeting with Students for Opinions

1 day

Tue 13-02-18

Tue 13-02-18

5

      Approval of the Project

1 day

Wed 14-02-18

Wed 14-02-18

6

      Appoint Stakeholders for Project

2 days

Thu 15-02-18

Fri 16-02-18

7

      Conduct Survey

2 days

Mon 19-02-18

Tue 20-02-18

8

      Estimate Possible Revenue Cap

1 day

Wed 21-02-18

Wed 21-02-18

9

   Phase 2: Initiation

9 days

Thu 22-02-18

Tue 06-03-18

      Procure Funds for Event

5 days

Thu 22-02-18

Wed 28-02-18

10

      Procure Auditorium Hall for Event

2 days

Thu 01-03-18

Fri 02-03-18

12

      Assign Roles to Stakeholders

2 days

Mon 05-03-18

Tue 06-03-18

13

   Phase 3: Execution

47 days

Wed 07-03-18

Thu 10-05-18

      Preparation of Event Roadmap

2 days

Wed 07-03-18

Thu 08-03-18

14

      Invite Popular Figures to Perform in the Event

10 days

Fri 09-03-18

Thu 22-03-18

16

      Invite Representatives from Old Age Homes and Orphanages

5 days

Fri 23-03-18

Thu 29-03-18

17

      Invite students and their families

2 days

Fri 30-03-18

Mon 02-04-18

18

      Decorate the auditorium

5 days

Tue 03-04-18

Mon 09-04-18

19

      Prepare stage and audience zone

5 days

Tue 10-04-18

Mon 16-04-18

20

      Promote the Event

5 days

Tue 17-04-18

Mon 23-04-18

21

      Prepare students for performances

10 days

Tue 24-04-18

Mon 07-05-18

22

      Final Preparations

2 days

Tue 08-05-18

Wed 09-05-18

23

      Event Start

1 day

Thu 10-05-18

Thu 10-05-18

24

   Phase 4: Event

3 days

Fri 11-05-18

Tue 15-05-18

      Entrance of Audience

1 day

Fri 11-05-18

Fri 11-05-18

25

      Drama and Music Performances

0 days

Fri 11-05-18

Fri 11-05-18

27

      Lunch

0 days

Fri 11-05-18

Fri 11-05-18

28

      Academic Awards Ceremony

0 days

Fri 11-05-18

Fri 11-05-18

29

      Donation to Charity

0 days

Fri 11-05-18

Fri 11-05-18

30

      Ending of Event

0 days

Fri 11-05-18

Fri 11-05-18

31

      Collection of Revenue

1 day

Mon 14-05-18

Mon 14-05-18

32

      Signoff

1 day

Tue 15-05-18

Tue 15-05-18

33

   Phase 5: Closing

3 days

Wed 16-05-18

Fri 18-05-18

      Project Review

1 day

Wed 16-05-18

Wed 16-05-18

34

      Project Appraisal

1 day

Thu 17-05-18

Thu 17-05-18

36

      Official Closing

1 day

Fri 18-05-18

Fri 18-05-18

37

The risk management plan for the project has been prepared using the risk register matrix as follows.

Sl. no.

Risk

Probability

Severity

Effect Magnitude

Description

Precautions

1

Health Risk

3

5

15

Any event management team should always consider the health security risks on the hand for every activity, as an participant can face health issues at any point of time during the event

There should be enough availability of the first aid box since before the event started

2

Fire

5

5

25

Venue might catch fire due to any uncertainty and it could affect the whole set up including money loss and chaos among the auditions

Fire extinguisher should be well situated at the places where fire catching probability is high. Inflammable items should not be allowed within the venue

3

Emergency (Fire, Suffocation, etc.)

2

4

8

Emergency are the situations that might occur and audience needs to be evacuated with higher speed

Evacuation plan should be established during the fundraising event planning

4

Security

5

1

5

General safety is the always concern of the special events

For the cash and public safety volunteers should be recruited

5

General Risks

1

5

5

Fun is a fact for running any event successfully and without it audience might feel not good and leave the venue earlier

Stewards will be helpful in providing training to the host the event with fun and information

6

Communication

4

4

16

Communication lacking between the volunteer would left certain important concern behind

Assigning an individual for taking care of communication

7

Disable People

3

1

3

Disable people might reach to the event and special attention is always needed for them

Some volunteers should be individually assigned to a separate sector for disable people

8

Food Safety

5

4

20

Lack in food hygiene and availability could possibly affect the output of the event

Hygiene should be given importance and volunteers or catering services should allow foods ‘until they are not waste’

9

Facilities

4

5

20

Lack in food supplies, parking, sitting, and relaxing would affect the interest of the audience

All the comfort related matters should be taken care with high priority

10

Insufficient Donors

5

5

25

Lack in potential donors will affect the return on investment of the event

Potential donors should be targeted for the collection of enough budget to make the event successful

11

Overstressed workers

3

1

3

Volunteers lacking in delivering the objectives of the event would lead to deployment of work of low quality

Enough volunteers should be assigned equally to each sector of the event

12

Over- Resourcing

3

3

9

The resources should be made available as per the requirement of the event and present population as it will affect the budget of the project unnecessarily

Resource allocation should be well arranged as per the population and needs of the  event

13

Return on Investment

1

1

1

Lacking in return on investment would affect the feasibility and success of the organized fundraising event

Investment should be made according to the return that the event will provide to the volunteers or organizers

Risk Matrix:

Probability

5

R.2

R.4

R.8

R.10

4

R.6

R.9

3

R.11

R.7

R.12

R.1

2

R.13

R.3

R.5

1

Severity

1

2

3

4

5

The communication management plan is shown in the following table.

Stakeholder

Communication Frequency

Communication Mode

Reason of Communication

Project Manager

Daily

Daily Reports

Frequent updates on project

Finance Manager

Weekly

Finance Sheets

Budget requirements

Event Manager

Daily

Verbal

Event requirements

Site Manager

Before Start of Project

Verbal, Contract

Site requirements

Rewards Manager

During the Event

Verbal

Rewards to be given to participants

Conclusion

In this report, a detailed project plan has been provided for the fundraising event to be conducted at the end of the academic year. The project plan includes determination of the project objectives and scope, constraints and assumptions, project charter, stakeholder analysis and risk analysis. According to the plan, the fundraising event will be hosted along with the final day of the academic year. On this day, rewards will be given to the best performers during the academic course based on the marks scored in the evaluations, overall performances and other attributes. However, this year, the event will be extended and there will be several stage performances of music, drama and others. While some popular figures will be invited to take part in the event, other performances will be done by the students of the college.

As per the proposed plan for the project, the following recommendations can be made.

  • Before proceeding with the project, it must be ensured that sufficient revenue can be generated from the event.
  • Feasibility test must be conducted in order to ensure the project is feasible for the organization.

Boud, D., Cohen, R. and Sampson, J. eds., 2014. Peer learning in higher education: Learning from and with each other. Routledge.

Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.

Fuller, M.A., Valacich, J.S., George, J.F. and Schneider, C., 2017. Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.

Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.

Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Leach, L.P., 2014. Critical chain project management. Artech House.

Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Taylor & Francis.

Pinto, J.K., 2015. Project management: achieving competitive advantage. Prentice Hall.

Schwalbe, K., 2015. Information technology project management. Cengage Learning.

Snyder, C.S., 2014. A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.

Turner, R., 2016. Gower handbook of project management. Routledge.

Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.

Walker, A., 2015. Project management in construction. John Wiley & Sons.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.