Project Management For 3-Day Sydney Holiday With Friends
NBC3101-Objectives and Scope of the Project
NBC3101-Objectives and Scope of the Project
Project Objectives
The report aims in development of a schedule and cost plan for five friends who are travelling to Sydney for a holiday for 3 days. For this project, a schedule for 72 hours has been prepared. Certain assumptions are made while developing the schedule for the project. The report identifies the scope and objectives of the project and delivers a work breakdown structure. The sequence of activities are presented in the report in form of a work breakdown structure. A schedule Gantt chart has been prepared for the project as well. The cost of each and every activities of the tour is calculated and the details are indicated in form of a cost table.
The objectives “Travelling to Sydney” project are as follows-
- To develop a schedule for the Project
- To estimate the time required for completion of each activity
- To estimate the cost of the entire project
The in-scope requirements of “Travelling to Sydney” project are as follows-
- To ascertain that the project is completed in 72 hours
- To ascertain that the project is executed in the allocated budget. Each friend has a budget of AUD 1500, which indicates that the total budget of the project is AUD 7500
- The schedule estimate includes the travelling and the resting time
The out-scope requirements of the project are as follows-
- The estimation has no scope for adding other activities apart from those mentioned in the schedule
- There is no scope of extending the holiday as the budget of the project is fixed
The schedule estimation is done considering both in-scope and out-scope requirements of the project. Certain assumptions are considered for developing the schedule of the project, which are discussed in the later section of this report.
The WBS of the project, generated from project scheduling is represented in the picture below-
Figure 1: Showing the Work Breakdown Structure of Travelling to Sydney Project
The work breakdown structure in the figure above represents the works to be completed in a time span of three days.
The time for completion of the activities related to “Travelling to Sydney Project” and their sequence is indicated in the table below-
Task Name |
Duration |
Start |
Finish |
Predecessors |
Travelling to Sydney |
72 hrs |
Mon 25-03-19 |
Thu 28-03-19 |
|
Start of Journey |
1 hr |
Mon 25-03-19 |
Mon 25-03-19 |
|
Arriving at Sydney |
2 hrs |
Mon 25-03-19 |
Mon 25-03-19 |
1 |
Checking in to the Hotel |
1 hr |
Mon 25-03-19 |
Mon 25-03-19 |
2 |
Day 1 Activities |
20 hrs |
Mon 25-03-19 |
Tue 26-03-19 |
|
Breakfast in Hotel |
1 hr |
Mon 25-03-19 |
Mon 25-03-19 |
3 |
Walking tour in Darling Harbour |
2 hrs |
Mon 25-03-19 |
Mon 25-03-19 |
5 |
Walking Tour in Circular Quay |
2.5 hrs |
Mon 25-03-19 |
Mon 25-03-19 |
6 |
Lunch |
1.5 hrs |
Mon 25-03-19 |
Mon 25-03-19 |
7 |
Boating Tour of Sydney Harbour |
2 hrs |
Mon 25-03-19 |
Mon 25-03-19 |
8 |
Travelling to Cockatoo Island and Sight Seeing |
3 hrs |
Mon 25-03-19 |
Tue 26-03-19 |
9 |
Returning to Hotel |
1 hr |
Tue 26-03-19 |
Tue 26-03-19 |
10 |
Dinner |
1 hr |
Tue 26-03-19 |
Tue 26-03-19 |
11 |
Resting At hotel |
6 hrs |
Tue 26-03-19 |
Tue 26-03-19 |
12 |
Day 2 Activities |
24 hrs |
Tue 26-03-19 |
Wed 27-03-19 |
|
Breakfast in Hotel |
1 hr |
Tue 26-03-19 |
Tue 26-03-19 |
13 |
Tour to museum of Sydney |
4 hrs |
Tue 26-03-19 |
Tue 26-03-19 |
15 |
Lunch |
1.5 hrs |
Tue 26-03-19 |
Tue 26-03-19 |
16 |
Visiting the Sydney Cricket Ground |
2 hrs |
Tue 26-03-19 |
Tue 26-03-19 |
17 |
Travelling to Garigal National Park and sight seeing |
4 hrs |
Tue 26-03-19 |
Tue 26-03-19 |
18 |
Returning to Hotel |
3 hrs |
Tue 26-03-19 |
Wed 27-03-19 |
19 |
Dinner |
1.5 hrs |
Wed 27-03-19 |
Wed 27-03-19 |
20 |
Taking Rest |
7 hrs |
Wed 27-03-19 |
Wed 27-03-19 |
21 |
Day 3 Activities |
24 hrs |
Wed 27-03-19 |
Thu 28-03-19 |
|
Breakfast |
1 hr |
Wed 27-03-19 |
Wed 27-03-19 |
22 |
Travelling to Bondi Beach |
3 hrs |
Wed 27-03-19 |
Wed 27-03-19 |
24 |
Sight Seeing to Sydney Botanic Gardens |
3.5 hrs |
Wed 27-03-19 |
Wed 27-03-19 |
25 |
Lunch |
1.5 hrs |
Wed 27-03-19 |
Wed 27-03-19 |
26 |
Visiting the Rocks |
4 hrs |
Wed 27-03-19 |
Wed 27-03-19 |
27 |
Dinner |
2 hrs |
Thu 28-03-19 |
Thu 28-03-19 |
28 |
Checking out of the hotel |
2 hrs |
Thu 28-03-19 |
Thu 28-03-19 |
29 |
Travelling back and taking rest |
7 hrs |
Thu 28-03-19 |
Thu 28-03-19 |
30 |
End of the Journey |
0 hrs |
Thu 28-03-19 |
Thu 28-03-19 |
31 |
Table 1: Representing sequence of task and their duration
The predecessor in the table above indicates the sequence of the task, while the duration column indicates the total time required for completion of each project activity. In development of the task sequence, the holiday destinations that the friends have planned to visit is considered. The destinations include the major tourists’ attraction in Sydney. The time allocated for each activity is based on the total time the group of friends will be spending on Sydney. However, if there is a change in the tourists spots the friends are travelling to, the sequencing process can change as well. It is expected that the group of friends will be following this sequencing activity in order to ensure that their holiday to Sydney gets over within 3 days or 72 hours.
The scheduling of the project is indicated in the figure below-
Figure 2: Showing Gantt chart of Travelling to Sydney Project
The picture above indicates the project Gantt chart. The Gantt chart is generated with the help of a scheduling software MS Project. The Gantt chart represents the tasks or the activities that are involved with the holiday planning of the group of friends. From the Gantt chart in the above figure, it can be observed that every tasks are following a sequential structure. Therefore, each task associated with the Sydney project contributes to the critical tasks of the project. The schedule of the travelling to Sydney project is calculated in a way that the entire project is executed within the time of 72 hours. The Gantt chart of the project represents the start date and the end date of each activity associated with the holiday project. The time allocated for this project is in hours as it is assumed that the group of friends will be visiting the more than one tourist spot in a day.
The cost of each activity estimated for the project is represented in the table below-
Task Name |
Duration |
Resource Names |
Cost |
Travelling to Sydney |
72 hrs |
$7,450.00 |
|
Start of Journey |
1 hr |
A,B,C,D, Project Manager ,Travelling Expenses to Sydney[1] |
$500.00 |
Arriving at Sydney |
2 hrs |
A,B,C,D, Project Manager |
$0.00 |
Checking in to the Hotel |
1 hr |
Hotel Cost in two Instalments For Three Rooms[1] |
$900.00 |
Day 1 Activities |
20 hrs |
$950.00 |
|
Breakfast in Hotel |
1 hr |
Cost of Breakfast [1] |
$50.00 |
Walking tour in Darling Harbour |
2 hrs |
Cost of Sight Seeing in Darling Harbour[1] |
$50.00 |
Walking Tour in Circular Quay |
2.5 hrs |
Cost of tour to Circular Quay[1] |
$100.00 |
Lunch |
1.5 hrs |
Cost of Lunch [1] |
$100.00 |
Boating Tour of Sydney Harbour |
2 hrs |
Boating Tour to Sydney Harbour[1] |
$150.00 |
Travelling to Cockatoo Island and Sight Seeing |
3 hrs |
Expenses at Cockatoo Island[1],Travelling Expenses 1[1] |
$300.00 |
Returning to Hotel |
1 hr |
Travelling Expenses 2[1] |
$100.00 |
Dinner |
1 hr |
Cost of Dinner[1] |
$100.00 |
Resting At hotel |
6 hrs |
$0.00 |
|
Day 2 Activities |
24 hrs |
$1,500.00 |
|
Breakfast in Hotel |
1 hr |
Cost of Breakfast [1] |
$50.00 |
Tour to museum of Sydney |
4 hrs |
Boating Tour to Sydney Harbour[1] |
$150.00 |
Lunch |
1.5 hrs |
Cost of Lunch [1] |
$100.00 |
Visiting the Sydney Cricket Ground |
2 hrs |
Expenses in Sydney Cricket Ground[1],Travelling Expenses 3[1] |
$500.00 |
Travelling to Garigal National Park and sight seeing |
4 hrs |
Expenses at Garigal National Park [1],Travelling Expenses 4[1] |
$450.00 |
Returning to Hotel |
3 hrs |
Travelling Expenses 5[1] |
$150.00 |
Dinner |
1.5 hrs |
Cost of Dinner[1] |
$100.00 |
Taking Rest |
7 hrs |
$0.00 |
|
Day 3 Activities |
24 hrs |
$3,600.00 |
|
Breakfast |
1 hr |
Cost of Breakfast [1] |
$50.00 |
Travelling to Bondi Beach |
3 hrs |
Cost of Activities At Bondi Beach[1],Travelling Expenses 6[1] |
$1,300.00 |
Sight Seeing to Sydney Botanic Gardens |
3.5 hrs |
Sight Seeing Cost at Botanic gardens[1],Travelling Expenses 7[1] |
$500.00 |
Lunch |
1.5 hrs |
Cost of Lunch [1] |
$100.00 |
Visiting the Rocks |
4 hrs |
Cost of expense at Rocks [1] |
$500.00 |
Dinner |
2 hrs |
Cost of Dinner[1] |
$100.00 |
Checking out of the hotel |
2 hrs |
Hotel Cost in two Instalments For Three Rooms[1] |
$900.00 |
Travelling back and taking rest |
7 hrs |
Travelling expenses back from Sydney[1] |
$150.00 |
End of the Journey |
0 hrs |
$0.00 |
Table 2: Representing the Cost Estimation of the Project
The figure that is indicated below is representing the project cost in Gantt chart view –
Figure 3: Representing the Project Cost in Gantt chart View
The table and the figure above indicates that the total cost of the project is $7,450. Thus, it is possible to complete the project within the set budget of $7,500. The budget of the project is set on basis of the money available with the group of friends. While estimating the cost, a standard rate for breakfast, lunch and dinner is considered.
The schedule and cost estimation of “Travelling to Sydney Project” involves certain major assumptions which are as follows-
- The cost of travelling, lunch, dinner and other activities are considered for 5 people
- It is assumed that the holiday will not be extended beyond 72 hours
- It is assumed that hotel and travelling cost will not change during project implementation.
- The entire scheduling activity is done with the help of the scheduling software MS project. While scheduling the activities, a 24 hours format is chosen for the scheduling activity. The scheduling involves the resting time of the group of friends as well.
Conclusion
The report discusses the schedule and the resource needs of holiday in Sydney for 72 hours. A group of five friends are going on a holiday and therefore, cost of every task is estimated on basis of five people. The report gives an idea of the objectives and scope of the project. The details of schedule estimation is discussed in the report along with the details of cost. It is observed that the travelling to Sydney project is completed in a budget of $7,500. However, certain assumptions are considered for developing the schedule and the budget, which are discussed in the report as well. The group of friends are expected to follow the schedule prepared in order to spend their holiday within the set budget.
Crawford, J.K., 2014. Project management maturity model. Auerbach Publications.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Milosevic, D.Z. and Martinelli, R.J., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), pp.1382-1394.