Portfolio Of Evidence For Workplace Project Management Process

Determine Project Parameters

Project Management has always been helpful for executing the project in an orderly process for easing the implication of the operations. The scheduling, planning, budgeting, estimating, and managing of the projects are well executed for developing the successful completion of the project. The support and development of the projects had eased the implication and alignment for developing the support for improving the utilization of the factors. The alignment would also be helpful for supporting the development of the options for aligning with the implication of the effective project management principles for the project of 24X7 facilities and services in the upper west side. The following assignment would be developed based on the implication of the facilities defining the implication of the operations and aligning the utilization of the factors.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The following assignment has been made for implementing the 24X7 facilities and services in the upper west side. The alignment would be dependent on forming the support and implementation of the effective alignment of the facilities. The improved services in the building would be installed for developing the improved facilities and operations. The successful alignment would be helpful for easing the implication of the factors defining the support and influence of activities. The completion of the improved functional analysis would form the major impact on the alignment of the support and configuration of the options. The camera services, Existing camera is reviewed, development of information hub, ordering keys and swipes, developing parcel delivery system, improving general cleanliness, upgrade lightning and design, BBQ area signage, and Madison Tower Level Upgrade. The implication of the activities would help in easing the alignment of the factors defining the alignment of the improved services for the complex building.

The project has the primary objective of defining the implication of the improved facilities and aligning the utilization of the factors. The project objective would include the factors of developing the improved services for the development of the factors. The implication would be eased with the utilization of the support and development. The deployment would be eased with the utilization of the factors aligning the development of the support and integration. The support and integration would be utilized for easing the implication and alignment of operations so that the improved functional development can be achieved. The negotiation with the client on objectives and timeline of the project would be based on the implication of the factors defining the analysis of the support and development. The analysis of the factors would be affected by the simplification of the support and development.

The stakeholders of the project are Owners Corporation 1, Owners Corporation 2, Owners Corporation 4, Owners Corporation 5, Owners Corporation 6, Owners Corporation 7, and Australian Property Management Pty Ltd.

The following table would show the roles and responsibilities of the individual for the execution of the project.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Name

Roles and Responsibilities

Shawn Lu – Australian Property Management Pty Ltd

Management of the project and execution for successful completion of the project

Esin Ibrahim – Australian Property Management Pty Ltd

In charge of project resources and estimation of the budget required for the project

Lip Phua – Australian Property Management Pty Ltd

Scheduling and Planning the project for ensuring the smooth operations of the service development for upper west side

Justin Barr – Australian Property Management Pty Ltd

Making required documentation and reports that would be helpful for executing the project activities.

Tapan Reang – Australian Property Management Pty Ltd

Supporting documentation and development for easing development of the factors for developing the implication of the operations and aligning the development of the factors.

Carla Nessel – Australian Property Management Pty Ltd

Execution of the development and renovation activities for easing the formation of the utilities to form the extension of the operations

Paul Alabach – Australian Property Management Pty Ltd

Deploying the utilization of the factors developing the alignment of the improved functional and effective development of operations

Sonia Arora – Australian Property Management Pty Ltd

In charge of HR activities for developing the successful integration of the functions aligning the significant formation of improved activities

The project of 24X7 facilities and services in the upper west side is developed for improving the functional analysis of the factors supporting the utilization of the support and development. The deliverables of the project are,

Negotiation of Project Objectives and Timeline and Identification of Client and Stakeholders

Security Camera Upgrade: The security camera upgrade would be developed for aligning with the development of the facilities for aligning the implication of the effective and smart processing.

Community Hub: The community hub would be developed for supporting the effective communication and alignment of the factors supporting the implication of the improved operations.

Improvement of general cleanliness: The general cleanliness would be improved with the help of the innovative technology and new management installation.

Upgrade lightning and design: The upgrade of the lightning and design would be required for the technology innovation and development of the factors aligning the simplification.

BBQ area signage: The BBQ area signage would be developed for easing the utilization of the development factors for general meeting and communication development.

Madison Tower Level Upgrade: The tower level would be upgraded with the general alignment of the technology development and execution.

Reduction in Levies Owning: The reduction of the levies owning would be eased in the project activities execution and development.

The project has the primary goal of defining the implication of the improved facilities and aligning the utilization of the factors. The project goal would include the factors of developing the improved services for the development of the factors. The implication would be eased with the utilization of the support and development. The deployment would be eased with the utilization of the factors aligning the development of the support and integration. The support and integration would be utilized for easing the implication and alignment of operations so that the improved functional development can be achieved.

The strategies used for the development of the project activities would be eased with the implication of the facilities defining the alignment of the improved factors. The scheduling, planning, budgeting, estimating, and managing of the projects are well executed for developing the successful completion of the project. The support and development of the projects had eased the implication and alignment for developing the support for improving the utilization of the factors. The alignment would also be helpful for supporting the development of the options for aligning with the implication of the effective project management principles for the project of 24X7 facilities and services in the upper west side.

The monitoring and reporting of the project of 24X7 facilities and services in the upper west side would be deployed with the help of easing the implication of the factors of  supporting the implication of the factors aligning the definition of the activities favouring the alignment of the activities. The use of the Gantt chart and checklist would be helpful for keeping track of the project progress and schedule. The use of various testing processes like alpha testing, beta testing, prototyping, and simulation would be helpful for easing the development of the activities. The various strategies of monitoring and reporting in the project include,

Baseline Report: The baseline report is helpful for ensuring that the effective communication process is implied successfully. The support and development would also be helpful for easing the process of the keeping track of the project activities. For example: the report would help in checking how much work of the project has been completed after time interval of one fourth, half, three fourth, and full completion of the estimated time.

Roles and Responsibilities

Checklist Development: The checklist development would be helpful for easing the utilization of effective implication management. The checklist would be developed keeping in mind the implication of the successful completion of the operations. For example- the developed checklist would keep track of the achievement of the deliverables of plan, documentation, infrastructure, technology, equipments, and final report.

Progress Journal: The progress journal is helpful for noting the day to day activities and aligning the implication of the successful development of the factors. The progress journal would allow the implication of the factors for easing the utilization of the operations. For example- the progress journal would help in back tracking the problem of schedule and change it so that the rest of the project can be completed successfully.

                       

                                                              Figure 1: Project Life Cycle Analysis

                                                                                   Source:

The risk management plan would be developed aligning the utilization of the factors defining the simplification of the factors supporting the utilization of the factors aligning the simplicity of the activities deploying the utilization of the factors developing the simplification of the operations. The risk management plan comprises of risk analysis and risk mitigation for supporting the utilization of the factors defining the implication of the operations. The risk management would involve the following factors,

Risk

Cause of the risk

Likelihood

Severity

Mitigation

Ranking

Delay in completion

The delay can be resulted by many reasons such as lack of the materials, human errors, or equipment failure that would result in halting the progress of the project.

Likely

Moderate

Accept

3rd

Over budget

The over budget is resulted due to the lack of the proper development process and inclusion of the effective implication of the factors.

Possible

Major

Avoid

2nd

Technology Issues

The technology issues are resulted when the equipments fail to involve the alignment of the operations and significant development of the factors. The device may fall short for aligning the simplification and developed operations

Unlikely

Critical

Mitigate

1st

The 24X7 facilities and services in the upper west side project would be based on the ground works and the technology innovation implementation. The following legislative requirements must be followed for the project,

  • Abiding to the community welfare and development process for easing the implication of the new services
  • Following the safety policies and procedures for the emergency exits and safety drills
  • Aligning the implication of the factors defining the utilization of the innovative technology development
  • According to Industry and Technology Development Act 1988, the encouragement of the facility for residential and commercial section should be used
  • According to Western Australian Products Symbol Act 1972, the development is based on the prescribed promotion of the products

The 24X7 service technology implementation for Upper West Side project would involve the use of the technology innovation for development of the effective plan development supporting the implication of the improved development process. The following is the project plan for the improved facilities and services of upper west side, ordering keys and swipes, development of information hub, developing parcel delivery system, improving general cleanliness, upgrade lightning and design, BBQ area signage, and Madison tower level upgrade. 

WBS

Task Name

Duration

Start

Finish

Predecessors

0

24X7 service technology implementation for Upper West Side

61 days

Thu 11/16/17

Thu 2/8/18

1

Initialization

8 days

Thu 11/16/17

Mon 11/27/17

1.1

Project Analysis

2 days

Thu 11/16/17

Fri 11/17/17

1.2

Resource Accumulation

3 days

Mon 11/20/17

Wed 11/22/17

2

1.3

Initiation documents

2 days

Thu 11/23/17

Fri 11/24/17

3

1.4

Submission of documents

1 day

Mon 11/27/17

Mon 11/27/17

4

1.5

Project Kick off

0 days

Mon 11/27/17

Mon 11/27/17

5

2

Planning

13 days

Tue 11/28/17

Thu 12/14/17

2.1

Activity Listing

2 days

Tue 11/28/17

Wed 11/29/17

6

2.2

Scheduling the activities

1 day

Thu 11/30/17

Thu 11/30/17

8

2.3

Plan Outline Development

3 days

Fri 12/1/17

Tue 12/5/17

9

2.4

Review of Plan

2 days

Wed 12/6/17

Thu 12/7/17

10

2.5

Complete Plan Development

5 days

Fri 12/8/17

Thu 12/14/17

11

2.6

Plan Approval

0 days

Thu 12/14/17

Thu 12/14/17

12

3

Execution

34 days

Fri 12/15/17

Wed 1/31/18

3.1

Security Camera Upgrade

10 days

Fri 12/15/17

Thu 12/28/17

3.1.1

Existing Camera is reviewed

2 days

Fri 12/15/17

Mon 12/18/17

13

3.1.2

Upgrading the camera function

4 days

Tue 12/19/17

Fri 12/22/17

16

3.1.3

Additional and multiple cameras are installed

4 days

Mon 12/25/17

Thu 12/28/17

17

3.2

Community Hub

9 days

Fri 12/29/17

Wed 1/10/18

3.2.1

Development of Information Hub

3 days

Fri 12/29/17

Tue 1/2/18

18

3.2.2

Ordering Keys and Swipes

2 days

Wed 1/3/18

Thu 1/4/18

20

3.2.3

Developing parcel delivery system

4 days

Fri 1/5/18

Wed 1/10/18

21

3.3

Other Works

15 days

Thu 1/11/18

Wed 1/31/18

3.3.1

Improving general cleanliness

3 days

Thu 1/11/18

Mon 1/15/18

22

3.3.2

Upgrade lightning and design

3 days

Tue 1/16/18

Thu 1/18/18

24

3.3.3

BBQ area signage

3 days

Fri 1/19/18

Tue 1/23/18

25

3.3.4

Madison Tower Level Upgrade

3 days

Wed 1/24/18

Fri 1/26/18

26

3.3.5

Reduction in Levies Owning

3 days

Mon 1/29/18

Wed 1/31/18

27

4

Closure

6 days

Thu 2/1/18

Thu 2/8/18

4.1

Final report is developed

3 days

Thu 2/1/18

Mon 2/5/18

28

4.2

Submission of reports

1 day

Tue 2/6/18

Tue 2/6/18

30

4.3

Review and sign off

2 days

Wed 2/7/18

Thu 2/8/18

31

4.4

Project is closed

0 days

Thu 2/8/18

Thu 2/8/18

32

The resources required for the execution of the project 24X7 facilities and services in the upper west side are given below,

Human

Materials

Project Manager, Planner, Budgeter, Documenter, Analyst, Technician, Material, and Contractor

Construction Materials, System, Camera, Other Devices

The project of 24X7 facilities and services in the upper west side is developed for improving the functional analysis of the factors supporting the utilization of the support and development. The deliverables of the project are,

Security Camera Upgrade: The security camera upgrade would be developed for aligning with the development of the facilities for aligning the implication of the effective and smart processing.

Community Hub: The community hub would be developed for supporting the effective communication and alignment of the factors supporting the implication of the improved operations.

Organize Support Processes

Improvement of general cleanliness: The general cleanliness would be improved with the help of the innovative technology and new management installation.

Upgrade lightning and design: The upgrade of the lightning and design would be required for the technology innovation and development of the factors aligning the simplification.

BBQ area signage: The BBQ area signage would be developed for easing the utilization of the development factors for general meeting and communication development.

Madison Tower Level Upgrade: The tower level would be upgraded with the general alignment of the technology development and execution.

Reduction in Levies Owning: The reduction of the levies owning would be eased in the project activities execution and development.

WBS

Task Name

Duration

Start

Finish

Predecessors

0

24X7 service technology implementation for Upper West Side

61 days

Thu 11/16/17

Thu 2/8/18

1.5

Project Kick off

0 days

Mon 11/27/17

Mon 11/27/17

5

2

Planning

13 days

Tue 11/28/17

Thu 12/14/17

2.1

Activity Listing

2 days

Tue 11/28/17

Wed 11/29/17

6

2.2

Scheduling the activities

1 day

Thu 11/30/17

Thu 11/30/17

8

2.3

Plan Outline Development

3 days

Fri 12/1/17

Tue 12/5/17

9

2.4

Review of Plan

2 days

Wed 12/6/17

Thu 12/7/17

10

2.5

Complete Plan Development

5 days

Fri 12/8/17

Thu 12/14/17

11

2.6

Plan Approval

0 days

Thu 12/14/17

Thu 12/14/17

12

3

Execution

34 days

Fri 12/15/17

Wed 1/31/18

3.1

Security Camera Upgrade

10 days

Fri 12/15/17

Thu 12/28/17

3.1.1

Existing Camera is reviewed

2 days

Fri 12/15/17

Mon 12/18/17

13

3.1.2

Upgrading the camera function

4 days

Tue 12/19/17

Fri 12/22/17

16

3.1.3

Additional and multiple cameras are installed

4 days

Mon 12/25/17

Thu 12/28/17

17

3.2

Community Hub

9 days

Fri 12/29/17

Wed 1/10/18

3.2.1

Development of Information Hub

3 days

Fri 12/29/17

Tue 1/2/18

18

3.2.2

Ordering Keys and Swipes

2 days

Wed 1/3/18

Thu 1/4/18

20

3.2.3

Developing parcel delivery system

4 days

Fri 1/5/18

Wed 1/10/18

21

3.3

Other Works

15 days

Thu 1/11/18

Wed 1/31/18

3.3.1

Improving general cleanliness

3 days

Thu 1/11/18

Mon 1/15/18

22

3.3.2

Upgrade lightning and design

3 days

Tue 1/16/18

Thu 1/18/18

24

3.3.3

BBQ area signage

3 days

Fri 1/19/18

Tue 1/23/18

25

3.3.4

Madison Tower Level Upgrade

3 days

Wed 1/24/18

Fri 1/26/18

26

3.3.5

Reduction in Levies Owning

3 days

Mon 1/29/18

Wed 1/31/18

27

4.4

Project is closed

0 days

Thu 2/8/18

Thu 2/8/18

32

The communication in the project are developed supplying the alignment of the improved functional and development model. The communication in the project can be eased with the implication of the factors defining the synthesis of improved communication development. The communication would be eased with the simplification of the effective communication strategies like,

  • Transfer of information to the stakeholders with the help of email communication
  • Deployment of the support and development for the initiation of improved communication process
  • Alignment of the factors defining the simplification of the information processing and sharing
  • Innovative technology utilization for transferring the information

The various documents like initiation document, charter document, project plan document, communication list, risk management plan, development listing, formation plan, and other documents would be inclined for the development of project report.

The checklist for the project of 24X7 facilities and services in the upper west side is given below,

Item

Check

Gathering of initial information

Yes                        No

Resources are accumulated

Yes                        No

Alignment of operations and development of factors

Yes                        No

Project Plan is developed

Yes                        No

Infrastructure is developed

Yes                        No

Technology Innovation is installed

Yes                        No

The major problems for the execution of the project of 24X7 facilities and services in the upper west side are,

Delay in completion of the project is one of the most common issues that most of the projects have been facing in the contemporary world. However, the delay in projects would result in forming the major problems for project.

Over budget is another major problem that the project would have to face as it would result in forming the alignment of factors deploying the resource usage of the project.

The progress monitoring of the project of 24X7 facilities and services in the upper west side would be deployed with the help of easing the implication of the factors of  supporting the implication of the factors aligning the definition of the activities favouring the alignment of the activities. The use of the Gantt chart and checklist would be helpful for keeping track of the project progress and schedule. The use of various testing processes like alpha testing, beta testing, prototyping, and simulation would be helpful for easing the development of the activities. The implication of the activities would be eased with the utilization of the innovation.

OLD

NEW

Owners Corporation 1

Legal cost & debt recovery

$20,000.00

$5,000.00

Management Stationery

$4,500.00

$2,500.00

Office Telephone charges

$7,000.00

$3,000.00

Contingency line

$10,000.00

$0.00

Provision of Maintenance Fund

$10,000.00

$0.00

Insurance Recoverable

$10,000.00

$1,000.00

Insurance Premiums

$2,04,000.00

$2,60,000.00

Waste Compactor

$12,000.00

$55,000.00

Electricity

$18,000.00

$37,000.00

Water & Sewerage

$2,10,000.00

$4,00,000.00

$5,05,500.00

$7,63,500.00

Owners Corporation 2

Function Room Expenses

$7,50,000.00

$0.00

Contingency line

$5,000.00

$0.00

Management Stationery

$3,000.00

$1,000.00

General Maintenance

$25,000.00

$40,000.00

Gym equipment

$23,000.00

$60,000.00

Garden Maintenance

$51,000.00

$1,10,000.00

Electricity

$1,02,000.00

$1,44,000.00

$9,59,000.00

$3,55,000.00

Owners Corporation 4

Building Manager/Facilities

$4,02,200.00

$1,89,024.00

Auto Door Repairs

$10,000.00

$5,000.00

Steam Cleaning

$13,500.00

$17,000.00

Bin Chute Repairs

$6,000.00

$16,000.00

General Maintenance

$20,000.00

$30,000.00

Electricity

$92,000.00

$1,15,000.00

$5,43,700.00

$3,72,024.00

Owners Corporation 5

Building Manager/Facilities

$4,05,000.00

$1,89,024.00

Essential Services Repairs

$5,000.00

$15,000.00

Auto Door Repairs

$1,500.00

$7,000.00

Bin Chute Repairs

$3,000.00

$13,000.00

Electrical Repairs

$10,000.00

$18,000.00

General Repairs

$38,376.00

$30,000.00

Lift Repairs

$8,000.00

$15,000.00

Plumbing & drainage

$8,000.00

$15,000.00

478876

302024

Owners Corporation 6

Building Manager/Facilities

$4,04,300.00

$1,89,024.00

$4,04,300.00

$1,89,024.00

Owners Corporation 7

Building Manager

$1,58,000.00

$1,28,599.00

Rubbish Chute repairs

$20,000.00

$15,000.00

Electricity

$60,000.00

$70,000.00

$2,38,000.00

$2,13,599.00

$31,29,376.00

$21,95,171.00

The project would be executed under the supervision of the project manager, contractor, and Engineer for ensuring that the project is completed successfully in the estimated time and budget estimation.

WBS

Milestone

Start date

Finish date

Status

0

24X7 service technology implementation for Upper West Side

Thu 11/16/17

Thu 2/8/18

Completed

1.5

Project Kick off

Mon 11/27/17

Mon 11/27/17

Completed

2

Planning

Tue 11/28/17

Thu 12/14/17

Completed

2.1

Activity Listing

Tue 11/28/17

Wed 11/29/17

Completed

2.2

Scheduling the activities

Thu 11/30/17

Thu 11/30/17

Completed

2.3

Plan Outline Development

Fri 12/1/17

Tue 12/5/17

Completed

2.4

Review of Plan

Wed 12/6/17

Thu 12/7/17

Completed

2.5

Complete Plan Development

Fri 12/8/17

Thu 12/14/17

Completed

2.6

Plan Approval

Thu 12/14/17

Thu 12/14/17

Completed

3

Execution

Fri 12/15/17

Wed 1/31/18

Completed

3.1

Security Camera Upgrade

Fri 12/15/17

Thu 12/28/17

Completed

3.1.1

Existing Camera is reviewed

Fri 12/15/17

Mon 12/18/17

Completed

3.1.2

Upgrading the camera function

Tue 12/19/17

Fri 12/22/17

Completed

3.1.3

Additional and multiple cameras are installed

Mon 12/25/17

Thu 12/28/17

Completed

3.2

Community Hub

Fri 12/29/17

Wed 1/10/18

Completed

3.2.1

Development of Information Hub

Fri 12/29/17

Tue 1/2/18

Completed

3.2.2

Ordering Keys and Swipes

Wed 1/3/18

Thu 1/4/18

Completed

3.2.3

Developing parcel delivery system

Fri 1/5/18

Wed 1/10/18

Completed

3.3

Other Works

Thu 1/11/18

Wed 1/31/18

Completed

3.3.1

Improving general cleanliness

Thu 1/11/18

Mon 1/15/18

Completed

3.3.2

Upgrade lightning and design

Tue 1/16/18

Thu 1/18/18

Completed

3.3.3

BBQ area signage

Fri 1/19/18

Tue 1/23/18

Completed

3.3.4

Madison Tower Level Upgrade

Wed 1/24/18

Fri 1/26/18

Completed

3.3.5

Reduction in Levies Owning

Mon 1/29/18

Wed 1/31/18

Completed

4.4

Project is closed

Thu 2/8/18

Thu 2/8/18

Completed

The use of the Gantt chart and checklist would be helpful for keeping track of the project progress and schedule. The use of various testing processes like alpha testing, beta testing, prototyping, and simulation would be helpful for easing the development of the activities. The various documents like initiation document, charter document, project plan document, communication list, risk management plan, development listing, formation plan, and other documents would be inclined for the development of project report.

Monitor Project Processes and Outcomes

The strategies used for the development of the project activities would be eased with the implication of the facilities defining the alignment of the improved factors. The scheduling, planning, budgeting, estimating, and managing of the projects are well executed for developing the successful completion of the project. The use of various testing processes like alpha testing, beta testing, prototyping, and simulation would be helpful for easing the development of the activities. The support and development of the projects had eased the implication and alignment for developing the support for improving the utilization of the factors.

Item

Completed

Gathering of initial information

Yes

Resources are accumulated

Yes

Alignment of operations and development of factors

Yes

Project Plan is developed

Yes

Infrastructure is developed

Yes

Technology Innovation is installed

Yes

a) Utilization of the project management methodology

b) Proper Training Program Development

c) Implementing the use of past documents and reports

Sign off:

<name of the project manager>

<name of the project manager>

Project Manager

Conclusion

Project Management had always been helpful for executing the project in an orderly process for easing the implication of the operations. The scheduling, planning, budgeting, estimating, and managing of the projects were well executed for developing the successful completion of the project. The support and development of the projects had eased the implication and alignment for developing the support for improving the utilization of the factors. The following assignment had been made for implementing the 24X7 facilities and services in the upper west side. The alignment had been dependent on forming the support and implementation of the effective alignment of the facilities.

Berger, Bruce K., and Juan Meng, eds. Public relations leaders as sensemakers: A global study of leadership in public relations and communication management. Routledge, 2014.

Bessis, Joel. Risk management in banking. John Wiley & Sons, 2015.

Binder, Jean. Global project management: communication, collaboration and management across borders. Routledge, 2016.

Fleming, Quentin W., and Joel M. Koppelman. “Earned value project management.” Project Management Institute, 2016.

Goetsch, David L., and Stanley B. Davis. Quality management for organizational excellence. Upper Saddle River, NJ: pearson, 2014.

Harbor, Jason, Laurie Carswell Petrucci, and Tatiana Bourlova. “Assignment 3 Project Documentation:? Creating a Content Module for Calculus 12.” (2015).

Harrison, Frederick, and Dennis Lock. Advanced project management: a structured approach. Routledge, 2017.

Heagney, Joseph. Fundamentals of project management. Amacom, 2016.

Hopkin, Paul. Fundamentals of risk management: understanding, evaluating and implementing effective risk management. Kogan Page Publishers, 2018.

Jousse, Jérémie, Nicolas Ginot, Christophe Batard, and Elisabeth Lemaire. “Power line communication management of battery energy storage in a small-scale autonomous photovoltaic system.” IEEE Transactions on Smart Grid 8, no. 5 (2017): 2129-2137.

Kerzner, Harold, and Harold R. Kerzner. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons, 2017.

Kerzner, Harold. Project management best practices: Achieving global excellence. John Wiley & Sons, 2018.

Lam, J., 2014. Enterprise risk management: from incentives to controls. John Wiley & Sons.

Larson, Erik W., Clifford F. Gray, Ursula Danlin, Beverly Honig, and David Bacarini. Project management: The managerial process. Vol. 6. Grandview Heights, OH: McGraw-Hill Education, 2014.

MacWhinney, Brian. The CHILDES project: Tools for analyzing talk, Volume II: The database. Psychology Press, 2014.

Marchewka, Jack T. Information technology project management. John Wiley & Sons, 2014.

McNeil, Alexander J., Rüdiger Frey, and Paul Embrechts. Quantitative Risk Management: Concepts, Techniques and Tools-revised edition. Princeton university press, 2015.

Mir, Farzana Asad, and Ashly H. Pinnington. “Exploring the value of project management: linking project management performance and project success.” International journal of project management 32, no. 2 (2014): 202-217.

Mooney, Hailey, Jake Carlson, Karen Downing, and Lori Tschirhart. “Documentation in the Middle: Active Phase Project Documentation for Inclusive and Effective Team-Based Research.” (2017).

Nicholas, John M., and Herman Steyn. Project management for engineering, business and technology. Routledge, 2017.

Oliver, Kevin, and Jennifer Houchins. “Evidence of Computational Thinking in the After-School Makerspace from Written Project Documentation.” In EdMedia+ Innovate Learning, pp. 402-407. Association for the Advancement of Computing in Education (AACE), 2018.

O’Neill, Raymond. “Recommendations for Updating the Alaska Department of Transportation Construction Project Documentation Manual.” (2015).

Ruehl, Christopher Hendrik, and Diana Ingenhoff. “Communication management on social networking sites: Stakeholder motives and usage types of corporate Facebook, Twitter and YouTube pages.” Journal of Communication Management 19, no. 3 (2015): 288-302.

Svejvig, Per, and Peter Andersen. “Rethinking project management: A structured literature review with a critical look at the brave new world.” International Journal of Project Management 33, no. 2 (2015): 278-290.

Tench, Ralph, and Angeles Moreno. “Mapping communication management competencies for European practitioners: ECOPSI an EU study.” Journal of Communication Management 19, no. 1 (2015): 39-61.

Turner, Rodney. Gower handbook of project management. Routledge, 2016.

Verzuh, Eric. The fast forward MBA in project management. John Wiley & Sons, 2015.

Walker, Anthony. Project management in construction. John Wiley & Sons, 2015.

Wolke, Thomas. Risk Management. Walter de Gruyter GmbH & Co KG, 2017.

Wolke, Thomas. Risk Management. Walter de Gruyter GmbH & Co KG, 2017.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.