Project Planning And Development For Construction Of Regency Plaza Hotels And Condominiums

Part A: Project Contracts

According to Kubba (2010), the project planning and development had been largely helpful for the implication of the innovative and effective work completion. The project plan would be effectively implied with the formation of the project case study of ‘Construction of Regency Plaza Hotels and Condominiums’. The project management for construction projects would be required for the integration of the smart work alignment and development (Gorse & Emmitt, 2009). The following assignment would include the listing of the project contract management, project planning, controlling communication, and closure for the mentioned project. The document would support the successful transfer of the information to the required stakeholders.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Part A: Project Contracts

Legal benefits and Challenges of different types of contracts

The project contracts are helpful for developing the bond of work-fee between two or more parties (Forgues & Koskela, 2009). The participating parties would agree to deliver product/service to the other party in exchange of monetary benefits. The contract would also enable the stabilization of the advanced work alignment for the project of Construction of Regency Plaza Hotels and Condominiums. The contract management for the organization had been supported by the utilization of the contracts like Stipulated or lump-sum contract, Cost of work plus fee contract, Cost of work plus fee with guaranteed maximum price (GMP) contract, Construction management (CM) contract, and Design-build or design-and-construct (D&C) contract (Chen & Jin, 2012). These contracts have helped in gaining legal benefits along with some challenges as explained below.

Contract Type

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Legal benefits

Challenges

Stipulated or lump-sum contract

Single fixed price bid for all activities of project scope

Contractor would bear the risk associated with the project

Reducing the construction cost expense

Proposition of Unbalanced bids

Changes required for the scope and design deployment

Compensation requirement for early completion

Cost of work plus fee contract

It is budget friendly for the contractor

Cost can be reimbursed as the work is aligned

Limitation on the money expended by the contractor

Requirement of justification for each of the costs

No track of the indirect costs is another issue

Pre-decided profit would limit the scope for gaining more profit from the project

Cost of work plus fee with guaranteed maximum price (GMP) contract

Ease is procuring the contracts for the project

Easy accumulation of the funds for the project

Incentive option available for work completion

No mechanism for calculating the losses to the contractor

Losing the contract due to high pricing

Construction management (CM) contract

Inclusion of the responsibility for the expertise of entire management

The contract is continuous irrespective of the project manger

Confidentiality Disputes are common in this contract

Difficulty in management of the conflicts in the project

Design-build or design-and-construct (D&C) contract

Single Point Responsibility

Improved efficiency due to design and construction expertise

Few Changes are required as the implementation is simplified

Increased Flexibility

Owner Involvement is reduced

Extra cost of risk and contingencies plan

Limited qualified designer and builders

Larger and complex in nature

Mitigation of Challenges 

Contract Type

Challenges

Mitigation of the Challenges

Stipulated or lump-sum contract

Proposition of Unbalanced bids

Changes required for the scope and design deployment

Compensation requirement for early completion

Implication of the fair bid recognition should be implied

Negotiable Compensation method should be followed

Cost of work plus fee contract

Requirement of justification for each of the costs

No track of the indirect costs is another issue

Pre-decided profit would limit the scope for gaining more profit from the project

Cost management plan should be developed

Detail cost (both direct and indirect) should be used

Limited profit acquisition should be used

Cost of work plus fee with guaranteed maximum price (GMP) contract

No mechanism for calculating the losses to the contractor

Losing the contract due to high pricing

Contingency planning for the monetary losses

Optimized costing should be used

Construction management (CM) contract

Confidentiality Disputes are common in this contract

Difficulty in management of the conflicts in the project

Negotiation should be followed for contract development

Design-build or design-and-construct (D&C) contract

Owner Involvement is reduced

Extra cost of risk and contingencies plan

Limited qualified designer and builders

Larger and complex in nature

Effective communication strategies should be used

Training should be provided to the people

Complex project management should be used

Selection and Justification of the Design-Build-Contract

The contract of Design-Build-Contract should be used for the completion of the activities of the Construction of Regency Plaza Hotels and Condominiums project. The design bid build contract would allow the flexibility of the works for managing the change requirements, and implication of the smart work development and implication management (Carden & Boyd, 2012). The construction of the hotel rooms and condominiums would require inclusion of the design principles and construction of the facility.

Since, the project comprise of designing and constructing the building, floor, condominiums, and parking, the utilization of the design and build contract would be helpful for compiling work development. The single point responsibility in the design bid build contract would allow the manager/contractor to get the complete authorization over the project activities (Lester, 2014). The contract would help in improving the efficiency due to design and construction expertise for the construction project. Moreover, only few changes are required as the implementation is simplified using the contract which can be implemented due to the fact of increased flexibility.

Legal benefits and Challenges of different types of contracts

Project Pre-Planning

Identified Challenges and Mitigation Strategies of Project

The identified challenges for the Construction of Regency Plaza Hotels and Condominiums project and their mitigation strategies are given below,

Project Phase

Challenges

Type

Mitigation Strategy

Planning

Delay in building permit approval is a major issue that result in forming the major problems in completion of the project

Operational

Time Management Plan aligned with Project Baseline

Construction

Many minute changes in conceptual design had been resulting in forming change requirements for the project

Design

Change management plan should be used for effective change implication

Construction

Delay in construction of condominiums would result in causing loss to the organization

Operational

Time Management Plan aligned with Project Baseline

Construction

Rift between contractors (of hotel and condominiums) for worker distribution as the number of workers have reduced to 250 and the amount of work required for construction of hotel and condominiums is huge

Human

Effective Communication plan should be used for analyzing the requirements of both the contractor and hiring more workers for completion of the project on time

Finish

Unable to meet the punch list as the smaller items of the hotel and condominiums are not being equipped

Procurement

Continuous improvement plan steps should be followed for defining the works of the punch list

Approach for on-time delivery of project

As per the study of Levy (2010), the development of the project schedule and cost baseline report would be helpful for defining the estimated cost and time requirements for the Construction of Regency Plaza Hotels and Condominiums project. The on-time delivery of the project would include the formation of the task checklist so that the implication of the effective work alignment would be implied. The checklist development would enable the utilization of the monitoring of the project completion. The following approach should be used,

Step 1- Using MS-Project for making schedule for the project (for example: it would help in defining all activities of the project)

Step 2- Developing Task Checklist with expected durations (for example: it would help in keeping track of the project progress)

Step 3- Development of resource management and risk management plan

Step 4- Consider all contingency plan for the project

Step 5- Monitoring the project performance

Step 6- Change Management should be included

Step 7- Evaluation of the progress

Organization of Project cost

The project of Construction of Regency Plaza Hotels and Condominiums was set for the budget of $157m. The construction of the condominiums would be effectively implied with the implication of the resource usage. The project cost would be divided into human resource usage, Cost of material usage, contingency cost, and fixed cost (Olawale & Sun, 2010). The following is the budget management plan for the project,

Particulars

Standard rate

Duration/Units

Cost

Total

Human Resources

Project Manager

$450.00

250

$112,500.00

Designer for Hotel

$300.00

130

$39,000.00

Designer for Condominiums

$300.00

150

$45,000.00

Contractor for Hotel

$350.00

300

$105,000.00

Contractor for Condominiums

$350.00

350

$122,500.00

Workers (250 workers)

$110.00

1300

$35,750,000.00

Painter

$250.00

200

$50,000.00

Carpenter

$250.00

280

$70,000.00

Sub Total

$36,294,000.00

Material Resources

$0.00

Construction Materials

$150,000.00

250

$37,500,000.00

Equipment and Appliances

$130,000.00

400

$52,000,000.00

Others

$15,000.00

200

$3,000,000.00

Sub Total

$92,500,000.00

Fixed Cost

Electricity

$250,000.00

1

$250,000.00

Water utility

$200,000.00

1

$200,000.00

Transportation

$75,000.00

4

$300,000.00

Health and Safety

$100,000.00

5

$500,000.00

Sub Total

$1,250,000.00

Contingency

$20,807,040.00

Total Budget

$150,851,040.00

The project schedule has been developed using the MS-Project as a scheduling tool and the work breakdown structure identification can be done from the schedule developed below,

WBS

Task Name

Duration

Start

Finish

0

Construction of Regency Plaza Hotels and Condominiums

370 days

Mon 12/5/05

Fri 5/4/07

1

   Planning

61 days

Mon 12/5/05

Mon 2/27/06

1.1

      Requirement Analysis

10 days

Mon 12/5/05

Fri 12/16/05

1.2

      Bidding Process

15 days

Mon 12/19/05

Fri 1/6/06

1.3

      Hiring of Team Members

10 days

Mon 1/9/06

Fri 1/20/06

1.4

      Proposal

10 days

Mon 1/23/06

Fri 2/3/06

1.5

      Building Permit Approval

15 days

Mon 2/6/06

Fri 2/24/06

1.6

      Initial Meeting

1 day

Mon 2/27/06

Mon 2/27/06

1.7

      Kick off

0 days

Mon 2/27/06

Mon 2/27/06

2

   Construction

247 days

Tue 2/28/06

Wed 2/7/07

2.1

      Conceptual Design

17 days

Tue 2/28/06

Wed 3/22/06

2.2

      Detailed Design

24 days

Thu 3/23/06

Tue 4/25/06

2.3

      Floor Works

35 days

Wed 4/26/06

Tue 6/13/06

2.4

      Steel and Concrete Works

40 days

Wed 6/14/06

Tue 8/8/06

2.5

      22 storey construction

50 days

Wed 8/9/06

Tue 10/17/06

2.6

      96 Condominiums were built

60 days

Wed 8/9/06

Tue 10/31/06

2.7

      Underground Parking were built

30 days

Wed 11/1/06

Tue 12/12/06

2.8

      Hotel Room Division was built

16 days

Wed 12/13/06

Wed 1/3/07

2.9

      Installation of equipment and devices at rooms and condominiums

20 days

Thu 1/4/07

Wed 1/31/07

2.10

      Monitoring the facilities

5 days

Thu 2/1/07

Wed 2/7/07

2.11

      Completed

0 days

Wed 2/7/07

Wed 2/7/07

3

   Finish

62 days

Thu 2/8/07

Fri 5/4/07

3.1

      Interior and External Paints

20 days

Thu 2/8/07

Wed 3/7/07

3.2

      Finalize the works

8 days

Thu 3/8/07

Mon 3/19/07

3.3

      Drapes and Pillow works

10 days

Tue 3/20/07

Mon 4/2/07

3.4

      Counter Tops

5 days

Tue 4/3/07

Mon 4/9/07

3.5

      Finish Plumbing and Electric

12 days

Tue 4/10/07

Wed 4/25/07

3.6

      Complete Punch List

7 days

Thu 4/26/07

Fri 5/4/07

3.7

      Closed

0 days

Fri 5/4/07

Fri 5/4/07

The first column has shown the WBS id for each of the activity which can be used for the development of the WBD diagram as below The specific work packages has been explained below,

Work Package

Description

Activities Involved

Milestone

Planning

Initial analysis, documentation, and planning would be done in this phase

Requirement Analysis, Bidding Process, Hiring of Team Members, Proposal, Building Permit Approval, and Initial Meeting

Kick off

Construction

Constructing the hotel, Condominiums, and parking lot

Conceptual Design, Detailed Design, Floor Works, Steel and Concrete Works, 22 storeys construction, 96 Condominiums were built, Underground Parking were built, Hotel Room Division was built, Installation of equipment and devices at rooms and condominiums, and Monitoring the facilities

Completed

Finish

Final Closure of the project with last activities

Interior and External Paints, Finalize the works, Drapes and Pillow works, Counter Tops, Finish Plumbing and Electric, and Complete Punch List

Closed

Controlling Communication 

Communication Management Plan

The communication management plan would include the following steps for the project of Construction of Regency Plaza Hotels and Condominium,

Method of Communication

Sender

Receiver

Frequency

Information

Emails

Project client/manager

Project manager/team

Once

Change Request, Progress

Documents/Reports

Project team/manager

Project manager/client

Weekly

Project Issues, Progress, and Completion

Meetings

Project client/manager

Project manager/team

Once

Project Requirements

Addressing Project Stakeholder Expectations

The project stakeholder expectations would be addresses by the help of stakeholder engagement matrix,

Stakeholder

Interest

Power

Impact

Client (owner of regency plaza)

Project output meeting all scope items and quality

High

High

End User (renter/buyers of hotel rooms/condominium)

Use of the end product of project

Low

Low

Investors

Returns of the project investment

High

High

Project manager

Completion of the works

Low

High

The details of the project completion would be effectively implied with the formation of the development strategies (Levy, 2010). The analysis would be developed effectively for developing successful work alignment.

Contract Type

Role of Project Elements

Elements

Role

Schedule

Project Timeline for execution of the activities

Cost

Ensuring the usage of the resources

Quality

Ensuring the construction quality is met

Risk

Management of the risk factors

Lesson Learnt

The study had helped in understanding the importance of contract management, documentation, project planning, communication processes, and project closure. The use of MS-Project software for developing the project schedule, Gantt chart, and Network diagram had been effectively implied for taking care of the project completion. The study of the contracts for identifying the benefits of Stipulated or lump-sum contract, Cost of work plus fee contract, Cost of work plus fee with guaranteed maximum price (GMP) contract, Construction management (CM) contract, and Design-build or design-and-construct (D&C) contract.

Conclusion 

The study had helped in understanding the importance of contract management, documentation, project planning, communication processes, and project closure. The project of ‘Construction of Regency Plaza Hotels and Condominiums’ had been used for the analysis of the importance of the project management principles and techniques for effective construction management. The use of MS-Project software for developing the project schedule, Gantt chart, and Network diagram had been effectively implied for taking care of the project completion.

It had allowed the significant management of processes and defining the explicit management of the works. The study of the contracts for identifying the benefits of Stipulated or lump-sum contract, Cost of work plus fee contract, Cost of work plus fee with guaranteed maximum price (GMP) contract, Construction management (CM) contract, and Design-build or design-and-construct (D&C) contract. The pre-planning phase had evaluated the various possible issues and the challenges needed to address using the project management tools.

Carden, L. L. & Boyd, R. O. (2012). Ethical and legal considerations for project managers. Mustang Journal of Business & Ethics 3, 10-23. Retrieved from the Torrens University Australia Library database.

Chen, Q., & Jin, R. (2012). Safety4Site commitment to enhance jobsite safety management and performance. Journal of Construction Engineering & Management, 138(4), 509-519.

Forgues, D. & Koskela, L. (2009). The influence of a collaborative procurement approach using integrated design in construction on project team performance. International Journal of Managing Projects in Business, 2(3), 370-385.

Gorse, C. A. & Emmitt, S. (2009). Informal interaction in construction progress meetings. Construction Management and Economics, (27)10, 983-993.

Kubba, S. (2010). Green construction project management and cost oversight. Oxford: Architectural Press.

Lester, A. (2014). Project management, planning and control: managing engineering, construction and manufacturing projects to PMI, APM and BSI standards (6th ed.). Oxford: Butterworth-Heinemann.

Levy, S. M. (2010). Construction process planning and management. Oxford: Butterworth-Heinemann [D1, D2, A].

Olawale, Y. A. & Sun, M. (2010). Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Construction Management and Economics, 28(5), 509-526

Project Management Institute, Inc. (2007). Construction extension to the PMBOK Guide (3rd edition).

Sacks, R., Koskela, L., Dave, B. A. & Owen, Information modeling in construction. Journal of Construction Engineering and Management, 136(9), 968-980.

Sundaram, V. (2008). Essentials of design phase cost management and budget control. Cost Engineering 50(2), 24-28.

Tuuli, M. M., Rowlinson, S. & Koh, T. Y. (2010). Control modes and mechanisms in construction project teams: drivers and consequences. Construction Management and Economics, 28(5), 451-465.

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.