Project Charter For Setting Up A Cafe At Car Wash

Project Charter: Scope Overview

The report is associated with the description of a project that involves the setting up of a café at the car wash. The report consists of the discussions about the project charter. The main element of the business would be discussed in the report. The milestones and the success criteria for the projects are also discussed here.  The risks, assumptions and constraints, resources and the stakeholders and the lessons learned from the project are also included in the report.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The scope of this project is to accommodate a café in the car wash. The project would be able to provide the clients who come to the car wash an efficient scope of spending quality time in the café. This would increase the satisfaction of the customers towards the car wash company. However, the organization would be making sure that the customers would only be allowed to avail the services of the café only when they are availing the car wash services. The main point of focus for the organization would be the car wash services and not the café. Hence the project would be secondary focus and making the project a primary focus is out of scope.

In scope:

  • The construction of the new premises for the café
  • Feasibility study of the project
  • Furnishing of the café
  • Appointment of new coffee makers

Out of Scope:

  • Training of the staffs
  • Immediate expansion of the business

The Supercar Car Wash Facility is looking to implement a café in their car wash facility. The clients if the organization would be able to spend valuable time in the café while they would be required to wait for their car wash services to be completed (Kloppenborg 2015, p.87-88). This would provide the organization to avail some extra financial benefits and also increase the chances of improving the customer satisfaction towards the organization.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

This section is used for the discussions of the estimated schedule of the project. The table provide below would be helpful in providing an efficient insight to the progress of the project and also help in keeping track of the status of the project (Kloppenborg 2015, p.87-88). 

Milestone

Estimated Completion

Stakeholder Judge

Acceptance Criteria

Project Charter approved

20/03/2019

Owner

Discussions would take place in between the owners and the managing committee.

Final Design

07/05/2019

Project Manager

The qualification are to meet the best quality.

Raw materials and Ingredients Selection

10/05/2019

Operational Manager

The engineers and the interior designers.

Installation and Furnishing

12/05/2019

The interior Designer and the construction engineer associated with the project.

Fully functional coffee vending machines.

Testing and Sign-off

26/05/2019

The Interior Designer and the construction engineer associated with the project.

Sign-off after test

Related Documents

12/06/2019

Owner and the managing committee

The engineers and the interior designers.

Project close estimation

3/08/2019

Project Manager

Managing committee

The major risks involved with the project are to be identified in this section of the report and the other risks such as the risks that are involved with the cost and time of the projects (Kloppenborg 2015, p.94-95). There are other aspects of the projects as well such as the usefulness of the project deliverables. The risks identified in the systems are described in the table provided below:

Risk Description

Risk Rating (H/M/L)

Risk Owner

Response Plan

Equipment Failure (Coffee Vending Machines)

M

Technical Lead ( Kelly Brook)

1) Identification of the problems encountered

2) Replacement of the parts if required

Data theft or loss

H

Project Manager and Technical Staff (Prempratap Singh Dandiwal

, Kevin Owens)

Development of a data storage system in the future

Higher cost of Implementation

M

Accountant (Diana Parker)

Identification of the possible circumstances for the reduction of the costs for the development.

Lack of resources

H

Project Manager (Prempratap Singh Dandiwal)

Get external resources to fill the need

Inexperienced workers

M

Technical Staff (Kevin Owens)

1) Hire people with required experience

2) Designing of a strict hiring process.

In spite of identification of a number of risk further risks have also been identified for the project which is to be constructed for the development of the café in the car wash facility. The project team and the project manager would be equally responsible for the mitigation of the risks which are identified for the system.

  • Compatibility of the coffee vending machines with the other furnished products
  • Placement of the required instruments in the area
  • Missing out on the requirements of the project.

The resource section is concerned with the estimated value of the project budget and time line. Also the requirements of the human resources and supplies can be considered in this section (Kloppenborg 2015, p.97). The total cost required for acquiring the products and the equipment required for the project and total area required for the implementation of project are also to be taken into account in this section of the report. The table provided below is helpful in the estimation of the resources which are required in the project:

Resource Needed Estimate

People

Equipment

Money

Coffee suppliers

5x Coffee Vending Machines

= AUD 3000 x 5

Ingredients Supplier

Ingredients

=AUD 2500 x 1

5 x Card swiping machines

= AUD 850 x 5

Full Time Equivalent = 4.0 (FTE)

Total Equipment = 11

Total Cost = AUD 21,750

The estimations made above are done on a half yearly basis and the resources would alter a certain point of time.

The stakeholder’s analysis is done for the identification of the stakeholders who would be associated with the systems and would be affected by the implementation of the project (Kloppenborg 2015, p. 129). The table described below would be providing the details of the stakeholders who are associated with the project:

Stakeholder

Position

Interest

Priority

Patrick Miller

Owner

Overall project success

Key

Overall resources needed

Prempratap Singh Dandiwal

Project Manager

Overall cost

Key

Overall project success

Dean Jones

Construction Engineer

Development and construction of the premises

Key

Nick Jonas

Interior Designer

Designing of the interiors of the café

Key

Diana Parker

Accountant

Managing the finances for the project

Key

Prempratap Singh Dandiwal

Team Lead

Overall project success

Key

Project Team Co-ordination

Henry Cavil, Stuart Broad

Management committee

Overall project success

Key

Management of concerned areas of the project.

The section is involved with the discussions regarding the principles that are used during the project. The principles are responsible for the establishment of the factors on how the meetings for the project would be conducted and the process of treating other team members with respect (Kloppenborg 2015, p.97-98). The list of principles which are to be followed for the project are described below:

Efficient Communication Plan: The project team are required to develop an excellent project communication plan so that there is honesty in the perspective of each and every person.

Maintaining Project Schedule: The people should be able to maintain the schedule of the schedule of the project and complete the assigned tasks within the said time. This would make sure that no lag in the procedures of the project take place and the predecessors would also not suffer from scope creep.

Respect among the team members: The project team should be having a level of respect among each other and they should be able to treat each other with respect. The respect should be flowing from top to bottom level and vice versa. This can also improve the communication among the team members to a great extent.

Scope for learning and Improvements: The project should also provide a scope of learning and upgrading the project. The project team members should be able to learn from the project and also from the mistakes that were committed during the project so that this type of faults can be avoided in the future and the members would be gaining experience in the project management concepts and share their experience with their juniors in the future.  

Any type of successful project always possesses the features of having people who participate in the project who are skilful and have strengths in various type of fields. Hence, it is required that the project team consists of people who would able to work forward with the team in order to achieve the required outcomes from the projects (Kloppenborg 2015, p.98). The lessons learned from this project that would be passed on to the future projects are identified and listed below:

  • Participation in the project team meetings
  • Maintenance of an efficient project monitoring system.
  • Maintaining a proper project scope.

This section has been used for the authorizations of the approval made for the project by the project sponsor and also would be helpful in denoting the commitments made by the project team and the project manager.

Stakeholder

Position

Signature

Patrick Miller

Owner

Prempratap Singh Dandiwal

Project Manager

Dean Jones

Construction Engineer

Nick Jonas

Interior Designer

Diana Parker

Accountant

Prempratap Singh Dandiwal

Team Lead

Henry Cavil, Stuart Broad

Management committee

 

References

Kloppenborg, T.J. 2015, “Contemporary Project Management”, Cengage Learning, ed 3, pp. 90 – 121

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.